Burnham K50 manual Installation of Pilot Safety Switch, Pilot Piping EO Control System

Page 35

EO Control System

1.INSTALLATION OF PILOT SAFETY SWITCH AND

PILOT PIPING – Using two #10-32 x 2” MS and nuts, install the L62GB-3C pilot safety switch bracket on the manifold just to the right of the main burner with pilot.

Install L62GB-3C pilot safety switch on bracket using

Fig. 31

INSTALLATION OF PILOT SAFETY SWITCH

EO CONTROL SYSTEM

three #8 x ½” SMS. “IN” on pilot safety switch should be pointed in the direction of the Gas Train to which the pilot safety switch is to be connected, see Fig. 31.

Using ¼” OD Aluminum Tubing, connect the pilot valve installed in the manual shut-off valve in the gas train, to the inlet of the RV-12LT regulator (Packed in Gas Train Carton). Regulator should be above Gas Train and near front of boiler, see Fig. 32. Install 1/8” tee into outlet of regulator (USA boilers only) and, using ¼” OD tubing, connect outlet of tee to “IN” connection on pilotstat, see Fig. 32. Connect the Q309 thermocouple to pilot safety switch. Using ¼” OD aluminum tubing, connect the outlet of the pilotstat to the tubing or fittings connected to the pilot burner, see Fig. 32.

2.INSTALLATION OF BLEED PIPING – Using ¼” OD aluminum tubing, install a bleed line on both diaphragm valves, connect together, see Fig. 25 or 26 and run tubing to bleed line protruding from inside base, see Fig. 32. On boiler installed in Canada, run bleed line to outdoors.

3.INSTALLATION OF “EO” PANEL AND WIRING OF PILOT AND PILOTSTAT – Attach the EO mounting bracket with Controls, see Fig. 33, to both Upper and Lower Jacket End Panels, preferably on the same end as the Gas Train. Two holes in each Jacket Panel have been provided for this purpose. Use two #10-32 x ½”

Fig. 32

PILOT PIPING

EO CONTROL SYSTEM

35

Image 35
Contents Series 5B Section I Equipment Check List Important Information Canadian Equipment Check List Canadian Equipment Check List Natural GAS Maximum 14 W.C. Minimum 5.5 W.C Dimensional DataProvide Combustion and Ventilation AIR Do not Install this Boiler on CarpetingSingle Manifold Base 5006B Thru 5014B Section Boilers BASE-BURNER-MANIFOLD AssemblysDual Manifold Bases 5015B Thru 5026B Section Boilers LEH Section on Base Assembly of Center SectionsArrangement of Sections and Canopys Purpose of Tappings and Their Locations Open Steam or Water Trim CartonConnect Supply and Return Piping to Heating System Installation of BUILT-IN HeaterTesting Boiler Assembly for Leaks Oxygen Corrosion Sealing of BASE, Installation Flue Covers and CanopiesAttachment of Flue Covers Page Page Page Page Sizes 5006B Thru 5019B Recommended Water Boiler PipingSupply Connection & I Return Connection Supply Connections & 2 Return ConnectionsInstallation of Jacket Support Brackets to Base END Panels Installation of Jacket Parts Common to ALL Boiler SizesPage Exploded View of Jacket 6 Thru 10 Section Boilers Securing of CANOPY/DRAFTHOOD CANOPY/DRAFTHOOD Mounting Diagram Exploded View of Jacket 11 Thru 19 SECT. Boilers Completion of Jacket Installation 11 Thru 26 Section Boilers Exploded View of Jacket 20 Thru 22 SECT. Boilers Exploded View of Jacket 26 SECT. Boilers Steam Trim and Controls Shutoff Valve Between Safety ValveMounting Elevations of M&M 150 and a 67M Float Lwco Water Trim and Controls Open GAS Train Cartons Recommended Piping to BUILT-IN Tankless HeatersOpen Gas Controls Cartons Pilot Piping EI Control System Robertshaw7000 A B Thru 5009B Installation of S8610M ModuleA B Thru 5026B NAT. GAS Canada 5006B Thru 5026B NAT. GAS Pilot Piping EI Control System V88APilot Piping EO Control System Installation of Pilot Safety SwitchInstallation of Pilot Safety Switch EO Control System EE Control System Installation of EO and EE Mounting Bracket and ControlsPilot Piping EE Control System Sect. and larger boilersPilot Piping EOP Control System Installation of Pilot Safety Switch EOP Control SystemPilot Piping EEP Control System EEP Control SystemPage Single Vent System Manifold Vent System VentingPage General Section IV OperationTable IV Water Content Control Variations CondensationBe sure power is off when checking high voltage connections A B Thru 5009B Canada 5006B Thru 5014B Schematic Wiring Diagram EI Control System V88 GAS TrainSequence of Operation A B Thru 5014BEI Control System Schematic wiring diagram 15 Thru 26 SECT. BoilersSequence of Operation Page Pilot Failure Safety Switch CircuitWiring diagram 6 Thru 14 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring diagram 15 Thru 26 SECT. Boilers Operating and safety controls. Should any EE Control System Wiring diagram 15 Thru 26 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring Diagram 6 Thru 14 SECT. Boilers EOP Control System Turn on Main Power Switch. Main Power Light will light Wiring Diagram 15 Thru 26 SECT. Boilers EOP Control System Safety Switch Circuit Wiring Diagram 6 Thru 14 SECT. Boilers EEP Control System Pilot Failure Safety Switch Circuit Wiring Diagram 15 Thru 26 SECT. Boilers EEP Control System Make sure all manual resets are activated where applicable Normal Operation Sequence Page Check GAS Input Rate to Boiler Screw Minimum Input AdjustmentsV8944B Combination Valve Motorized Modulating ActuatorTest Ignition System Safety SHUT-OFF Device AS Follows Combustion Chamber BURN-OFF Thermocouple Pilot SystemRemoval of Jacket Front Panel Section V ServiceAvoid Breathing Fiber Particulates and Dust Lubrication Cleaning of FluewaysPilot Locations Honeywell Q179D Pilot w/THERMOCOUPLE Main Burner Flame AdjustmentPilot Flame Honeywell Q3481B Pilot FlameHoneywell Q327A Pilot w/THERMOCOUPLE Pilot Flame Honeywell Q179C PilotDo not drain water below gauge glass Jackets Base PartsNumber in in Table Relates to Corresponding Number Series 5B Base Parts 5006B thru 5014BBase Parts 5015B 5016B 5017B 5018B 5019B 5020B 5021B 5022B 5024B 5026B Series 5B Base Parts 5015B thru 5026BBase Parts Boiler Size Quantity Part Size CanopyIntegral Canopy Drafthoods & Sections Series 5B Section Replacement Chart Series 5B Base / Pilot Assemblies Series 5B Jackets 60413075 5007B Lower Top Panel 2 x 37-3/16 60413085 5008B 2 x 20-7/8 Complete Jackets Jackets Boiler Size 5006B 5008B 5009B 5014B 5015B 5016B 5017B 5026B Boiler SizeV88A GAS Trains Canada Natural GAS only Fluid Power GAS Trains USA 5006B 5009B 5015B 5016B 5017B 100Diaphragm Valve LO-HI-LO GAS Train Canada Natural GAS only 101102 Fluid Power GAS Trains CanadaIgnition Module & Support Bracket EI Control System 103Description Manifold Module Support L62GB-3C Pilot Safety Switch104 A. 5010B-5026B NAT. GAS Canada 5006B-5026B NAT. GAS 105Transformer & Pilot Line Regulator EO Control System 106107 108 109 110 EOP & EEP Control Panel 111112 EI Control System Pilot AssemblyEI GAS 1136236007 NAT. GAS Not Available for LP 1146236003 NAT. GAS 115 Date Service Performed116 Limited Warranty