Burnham K50 manual Water Trim and Controls

Page 30

g.If boiler has been ordered with 3/8” try-valve tapping, install try-cock.

h.Install “Lowest Permissible Water Level Plate” and “Frequent Water Addition – Caution Label” on upper left end jacket panel.

i.Proceed directly to Paragraph 36.

Fig. 26

Water TRIM AND CONTROLS

34.INSTALL WATER TRIM AND CONTROLS, see

Fig. 7 and 26.

a.Temperature Gauge is to be installed with ½” nipple and ½” x ¼” reducing coupling in ½” tapping provided in upper corner of End Section using wrench applied to square shank on back of gauge. DO NOT APPLY PRESSURE ON GAUGE GLASS.

b.Install Temperature Limit Controls as follows:

Bush 1-1/2” tapping in upper corner of End Section to ¾” and install Temperature Limit Control furnished following instructions supplied with control. On boilers without Built-in Tankless Heater, install second temperature limit control (not furnished) in Tapped Heater Opening Cover Plate. On boilers with Built-in Tankless Heater, install operating control in ¾” tapping in Heater Plate-plug tapping in Second Heater when supplied.

c.On boilers equipped for forced circulation hot water heating without domestic hot water, a reverse acting circulator control may be needed to prevent condensation of flue gases during periods of low boiler water temperature. This control can be installed in the Tapped Heater Opening Cover Plate.

d.TANKLESS HEATER PERFORMANCE

Tankless heater ratings in Series 5B boilers are based on continuous draw, temperature rise of 100ºF

30

(40-140ºF) and boiler water temperature of 200ºF. Some of the items affecting the coil performance are as follows:

(1)FLOW REGULATION – If flow through the heater is greater than its rating, the supply of adequate hot water may not be able to keep up with the demand. For this reason a FLOW REGULATOR matching the heater rating should be installed in the cold water line to the heater.

(2)FLUSHING OF HEATER - All water contains some sediment which settles on the inside of the coil. Consequently, the heater should be periodically back-washed. This is accomplished by installing hose bibs as illustrated and allowing water at city pressure to run into hose bib A, through the heater, and out hose bib B until the discharge is clear. The tees in which the hose bibs are located should be the same size as heater connections to minimize pressure drop.

(3)HARD WATER – This is applicable to some city water and particularly to well water. This should not be a deterrent but precautions are necessary. A water analysis is necessary and an appropriate water softener installed. This is not only beneficial to the heater but to piping and fixtures plus the many other benefits derived from soft water.

NOTE: A hot water boiler installed above radiation level must be provided with a low water cut-off device as part of the installation.

WARNING

Install automatic mixing valve at tankless heater outlet to avoid risk of burns or scalding due to excessively hot water at fixtures. Adjust and maintain the mixing valve in accordance with the manufacturers instructions.

e.Following recommendations supplied with control, install #64 Low Water Cut-Off in 1” pipe tapping

“H” (Fig. 7) and System Return Piping. Control must be mounted so that cut off point is above marking on Lowest Permissible Water Line Plate.

f.Install Pressure Safety Relief Valve, using fittings furnished, into 1-1/2” pipe tapping in upper corner of End Section. DO NOT INSTALL A SHUTOFF VALVE BETWEEN SAFETY RELIEF VALVE AND BOILER. Safety Relief Valve must be installed in a Vertical Position with handle up.

g.Install Boiler Drain Valve into one of unused return tappings that has been bushed to ¾”. Drain Valve can also be installed in return piping, preferably in leg of tee that is located in line with return connection on Boiler.

35.CONNECT PIPING TO BUILT-IN HEATER(S) IF USED, see Fig. 27.

Image 30
Contents Series 5B Section I Equipment Check List Important Information Canadian Equipment Check List Canadian Equipment Check List Dimensional Data Natural GAS Maximum 14 W.C. Minimum 5.5 W.CDo not Install this Boiler on Carpeting Provide Combustion and Ventilation AIRBASE-BURNER-MANIFOLD Assemblys Single Manifold Base 5006B Thru 5014B Section BoilersLEH Section on Base Assembly of Center Sections Dual Manifold Bases 5015B Thru 5026B Section BoilersArrangement of Sections and Canopys Open Steam or Water Trim Carton Purpose of Tappings and Their LocationsInstallation of BUILT-IN Heater Testing Boiler Assembly for LeaksConnect Supply and Return Piping to Heating System Sealing of BASE, Installation Flue Covers and Canopies Attachment of Flue CoversOxygen Corrosion Page Page Page Page Supply Connections & 2 Return Connections Recommended Water Boiler PipingSupply Connection & I Return Connection Sizes 5006B Thru 5019BInstallation of Jacket Parts Common to ALL Boiler Sizes Installation of Jacket Support Brackets to Base END PanelsPage Exploded View of Jacket 6 Thru 10 Section Boilers Securing of CANOPY/DRAFTHOOD CANOPY/DRAFTHOOD Mounting Diagram Exploded View of Jacket 11 Thru 19 SECT. Boilers Completion of Jacket Installation 11 Thru 26 Section Boilers Exploded View of Jacket 20 Thru 22 SECT. Boilers Exploded View of Jacket 26 SECT. Boilers Shutoff Valve Between Safety Valve Steam Trim and ControlsMounting Elevations of M&M 150 and a 67M Float Lwco Water Trim and Controls Recommended Piping to BUILT-IN Tankless Heaters Open GAS Train CartonsOpen Gas Controls Cartons Installation of S8610M Module Pilot Piping EI Control System Robertshaw7000 A B Thru 5009BPilot Piping EI Control System V88A A B Thru 5026B NAT. GAS Canada 5006B Thru 5026B NAT. GASInstallation of Pilot Safety Switch Installation of Pilot Safety Switch EO Control SystemPilot Piping EO Control System Installation of EO and EE Mounting Bracket and Controls EE Control SystemSect. and larger boilers Pilot Piping EE Control SystemInstallation of Pilot Safety Switch EOP Control System Pilot Piping EOP Control SystemEEP Control System Pilot Piping EEP Control SystemPage Venting Single Vent System Manifold Vent SystemPage Section IV Operation GeneralTable IV Water Content Condensation Control VariationsBe sure power is off when checking high voltage connections A B Thru 5009B A B Thru 5014B Schematic Wiring Diagram EI Control System V88 GAS TrainSequence of Operation Canada 5006B Thru 5014BSchematic wiring diagram 15 Thru 26 SECT. Boilers EI Control SystemSequence of Operation Page Safety Switch Circuit Pilot FailureWiring diagram 6 Thru 14 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring diagram 15 Thru 26 SECT. Boilers Operating and safety controls. Should any EE Control System Wiring diagram 15 Thru 26 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring Diagram 6 Thru 14 SECT. Boilers EOP Control System Turn on Main Power Switch. Main Power Light will light Wiring Diagram 15 Thru 26 SECT. Boilers EOP Control System Safety Switch Circuit Wiring Diagram 6 Thru 14 SECT. Boilers EEP Control System Pilot Failure Safety Switch Circuit Wiring Diagram 15 Thru 26 SECT. Boilers EEP Control System Make sure all manual resets are activated where applicable Normal Operation Sequence Page Check GAS Input Rate to Boiler Motorized Modulating Actuator Minimum Input AdjustmentsV8944B Combination Valve ScrewTest Ignition System Safety SHUT-OFF Device AS Follows Thermocouple Pilot System Combustion Chamber BURN-OFFSection V Service Removal of Jacket Front PanelAvoid Breathing Fiber Particulates and Dust Cleaning of Flueways LubricationPilot Locations Pilot Flame Main Burner Flame AdjustmentPilot Flame Honeywell Q3481B Honeywell Q179D Pilot w/THERMOCOUPLEPilot Flame Honeywell Q179C Pilot Honeywell Q327A Pilot w/THERMOCOUPLEDo not drain water below gauge glass Base Parts JacketsSeries 5B Base Parts 5006B thru 5014B Number in in Table Relates to Corresponding NumberBase Parts Series 5B Base Parts 5015B thru 5026B 5015B 5016B 5017B 5018B 5019B 5020B 5021B 5022B 5024B 5026BBase Parts Canopy Boiler Size Quantity Part SizeIntegral Canopy Drafthoods & Sections Series 5B Section Replacement Chart Series 5B Base / Pilot Assemblies Series 5B Jackets 60413075 5007B Lower Top Panel 2 x 37-3/16 60413085 5008B 2 x 20-7/8 Complete Jackets Jackets Boiler Size Boiler Size 5006B 5008B 5009B 5014B 5015B 5016B 5017B 5026BV88A GAS Trains Canada Natural GAS only Fluid Power GAS Trains USA 100 5006B 5009B 5015B 5016B 5017B101 Diaphragm Valve LO-HI-LO GAS Train Canada Natural GAS onlyFluid Power GAS Trains Canada 102103 Ignition Module & Support Bracket EI Control SystemPilot Safety Switch 104Description Manifold Module Support L62GB-3C 105 A. 5010B-5026B NAT. GAS Canada 5006B-5026B NAT. GAS106 Transformer & Pilot Line Regulator EO Control System107 108 109 110 111 EOP & EEP Control PanelEI Control System Pilot Assembly 112113 6236007 NAT. GASEI GAS 114 6236003 NAT. GASNot Available for LP Date Service Performed 115Limited Warranty 116