Burnham K50 Single Manifold Base 5006B Thru 5014B Section Boilers, BASE-BURNER-MANIFOLD Assemblys

Page 8

equipment in space. Duct cross-sectional area shall be same as opening free area.

3.Horizontal ducts. Minimum free area of 1 square inch per 2,000 Btu per hour input of all equipment in space. Duct cross-sectional area shall be same as opening free area.

Alternate method for boiler located within confined space. Use indoor air if two permanent openings communicate directly with additional space(s) of sufficient volume such that combined volume of all spaces meet criteria for unconfined space. Size each opening for minimum free area of 1 square inch per 1,000 Btu per hour input of all equipment in spaces, but not less than 100 square inches.

4.Louvers and Grilles of Ventilation Ducts

All outside openings should be screened and louvered. Screens used should not be smaller than ¼ inch mesh. Louvers will prevent the entrance of rain and snow.

a.Free area requirements need to consider the blocking effect of louvers, grilles, or screens protecting the openings. If the free area of the louver or grille

is not known, assume wood louvers have 20-25 percent free area and metal louvers and grilles have

60-75 percent free area.

b.Louvers and grilles must be fixed in the open position or interlocked with the equipment to open automatically during equipment operation.

SECTION III – INSTALLATION INSTRUCTIONS

Fig. 2

SINGLE MANIFOLD BASE 5006B

THRU 5014B SECTION BOILERS

1.BASE-BURNER-MANIFOLD ASSEMBLY(S).

a.6 section thru 14 section boilers require single base assembly, see Fig. 2.

b.15 section thru 26 section boilers require a left and a right base subassembly, see Fig. 3.

Remove Base Assembly(s) From Skid(s)

c.Remove bolts securing Base Assembly(s) to shipping skid(s) and place Base(s) in location where Boiler is to be installed.

d.Join Base Sub-assemblies together (15 section & larger boilers) by first removing upper shipping strip and lower shipping angles from subassemblies.

Use (4) ¼”-20 x ¾” MS, nuts and washers to attach subassemblies, see Fig. 3.

e.Attach Front Intermediate Jacket Panel Support Bracket and Lower Rear Intermediate Panel Support Bracket to lower channel on Front Base Frame and

Rear Base Frame, respectively, using (4) ¼”-20 x ¾” MS, nuts and washers.

f.Base must be level in both directions and secure on the floor. Shim and grout under Base if necessary.

g.Place cardboard covering over the top of the burner assembly to protect them during the assembly of the boiler sections.

2.CLEAN BOILER SECTIONS inside and out to remove dirt due to shipment and handling.

Open Tie Rod Bundle(s). Open Draw-up Rod Bundle(s).

Open Boiler Assembly Carton(s).

3.SET LEFT END SECTION ON BASE so that locating lugs on bottom of section go inside Front and Rear Base Frames. Slide section on base until these lugs strike High Base End Panel at left end of Base, see Fig. 4. (Note – if High Base End Panel is at right end of Base, section assembly must start with Right End Section).

Left end sections are identified by “LEH” cast on section; Right End Sections are identified by “REH” cast on section.

4.CLEAN NIPPLES AND NIPPLE PORTS thoroughly with a de-greasing solvent. Use the Loctite® #592 supplied to lubricate the nipples and nipple ports. Apply the lubricant to the nipples and nipple ports, then use a brush to disperse it evenly around the nipples and the nipple ports. Use approximately 25 ml of Loctite® #592 per flueway [(1) 7” and (2) 3” nipples and their

(6) corresponding nipple ports]. Use Nipple Gauge furnished – follow instructions included with gauge to set nipples. USE ALL PRECAUTIONS TO AVOID COCKED NIPPLES.

5.PAINT ALL GROUND SURFACES of each section with the Sealer Compound furnished.

6.ASSEMBLE CENTER SECTIONS. Refer to Fig. 6 for proper location of Tapped, and sometimes plugged, Center Sections on 11 section and larger boilers. THIS IS IMPORTANT.

Image 8
Contents Series 5B Section I Equipment Check List Important Information Canadian Equipment Check List Canadian Equipment Check List Dimensional Data Natural GAS Maximum 14 W.C. Minimum 5.5 W.CDo not Install this Boiler on Carpeting Provide Combustion and Ventilation AIRBASE-BURNER-MANIFOLD Assemblys Single Manifold Base 5006B Thru 5014B Section BoilersLEH Section on Base Assembly of Center Sections Dual Manifold Bases 5015B Thru 5026B Section BoilersArrangement of Sections and Canopys Open Steam or Water Trim Carton Purpose of Tappings and Their LocationsConnect Supply and Return Piping to Heating System Installation of BUILT-IN HeaterTesting Boiler Assembly for Leaks Oxygen Corrosion Sealing of BASE, Installation Flue Covers and CanopiesAttachment of Flue Covers Page Page Page Page Recommended Water Boiler Piping Supply Connection & I Return ConnectionSupply Connections & 2 Return Connections Sizes 5006B Thru 5019BInstallation of Jacket Parts Common to ALL Boiler Sizes Installation of Jacket Support Brackets to Base END PanelsPage Exploded View of Jacket 6 Thru 10 Section Boilers Securing of CANOPY/DRAFTHOOD CANOPY/DRAFTHOOD Mounting Diagram Exploded View of Jacket 11 Thru 19 SECT. Boilers Completion of Jacket Installation 11 Thru 26 Section Boilers Exploded View of Jacket 20 Thru 22 SECT. Boilers Exploded View of Jacket 26 SECT. Boilers Shutoff Valve Between Safety Valve Steam Trim and ControlsMounting Elevations of M&M 150 and a 67M Float Lwco Water Trim and Controls Recommended Piping to BUILT-IN Tankless Heaters Open GAS Train CartonsOpen Gas Controls Cartons Installation of S8610M Module Pilot Piping EI Control System Robertshaw7000 A B Thru 5009BPilot Piping EI Control System V88A A B Thru 5026B NAT. GAS Canada 5006B Thru 5026B NAT. GASPilot Piping EO Control System Installation of Pilot Safety SwitchInstallation of Pilot Safety Switch EO Control System Installation of EO and EE Mounting Bracket and Controls EE Control SystemSect. and larger boilers Pilot Piping EE Control SystemInstallation of Pilot Safety Switch EOP Control System Pilot Piping EOP Control SystemEEP Control System Pilot Piping EEP Control SystemPage Venting Single Vent System Manifold Vent SystemPage Section IV Operation GeneralTable IV Water Content Condensation Control VariationsBe sure power is off when checking high voltage connections A B Thru 5009B Schematic Wiring Diagram EI Control System V88 GAS Train Sequence of OperationA B Thru 5014B Canada 5006B Thru 5014BSchematic wiring diagram 15 Thru 26 SECT. Boilers EI Control SystemSequence of Operation Page Safety Switch Circuit Pilot FailureWiring diagram 6 Thru 14 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring diagram 15 Thru 26 SECT. Boilers Operating and safety controls. Should any EE Control System Wiring diagram 15 Thru 26 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring Diagram 6 Thru 14 SECT. Boilers EOP Control System Turn on Main Power Switch. Main Power Light will light Wiring Diagram 15 Thru 26 SECT. Boilers EOP Control System Safety Switch Circuit Wiring Diagram 6 Thru 14 SECT. Boilers EEP Control System Pilot Failure Safety Switch Circuit Wiring Diagram 15 Thru 26 SECT. Boilers EEP Control System Make sure all manual resets are activated where applicable Normal Operation Sequence Page Check GAS Input Rate to Boiler Minimum Input Adjustments V8944B Combination ValveMotorized Modulating Actuator ScrewTest Ignition System Safety SHUT-OFF Device AS Follows Thermocouple Pilot System Combustion Chamber BURN-OFFSection V Service Removal of Jacket Front PanelAvoid Breathing Fiber Particulates and Dust Cleaning of Flueways LubricationPilot Locations Main Burner Flame Adjustment Pilot Flame Honeywell Q3481BPilot Flame Honeywell Q179D Pilot w/THERMOCOUPLEPilot Flame Honeywell Q179C Pilot Honeywell Q327A Pilot w/THERMOCOUPLEDo not drain water below gauge glass Base Parts JacketsSeries 5B Base Parts 5006B thru 5014B Number in in Table Relates to Corresponding NumberBase Parts Series 5B Base Parts 5015B thru 5026B 5015B 5016B 5017B 5018B 5019B 5020B 5021B 5022B 5024B 5026BBase Parts Canopy Boiler Size Quantity Part SizeIntegral Canopy Drafthoods & Sections Series 5B Section Replacement Chart Series 5B Base / Pilot Assemblies Series 5B Jackets 60413075 5007B Lower Top Panel 2 x 37-3/16 60413085 5008B 2 x 20-7/8 Complete Jackets Jackets Boiler Size Boiler Size 5006B 5008B 5009B 5014B 5015B 5016B 5017B 5026BV88A GAS Trains Canada Natural GAS only Fluid Power GAS Trains USA 100 5006B 5009B 5015B 5016B 5017B101 Diaphragm Valve LO-HI-LO GAS Train Canada Natural GAS onlyFluid Power GAS Trains Canada 102103 Ignition Module & Support Bracket EI Control SystemDescription Manifold Module Support L62GB-3C Pilot Safety Switch104 105 A. 5010B-5026B NAT. GAS Canada 5006B-5026B NAT. GAS106 Transformer & Pilot Line Regulator EO Control System107 108 109 110 111 EOP & EEP Control PanelEI Control System Pilot Assembly 112EI GAS 1136236007 NAT. GAS Not Available for LP 1146236003 NAT. GAS Date Service Performed 115Limited Warranty 116