32.Tighten all sheet metal screws.

a.Install the following plates or labels which are found in the Instruction Envelope. See Fig. 23 or 24 for location.

(1)Rating Label

(2)Operating Instruction Plate (#8 SMS required to fasten)

(3)Combustible Clearance Flooring & Adequate Combustion Plate

(4)Minimum Service Clearance Label

(5)Burnham Logo – Apply to Top Panel

(6)Boiler Ventilation/For Your Safety Label

b.Proceed to Paragraph 33 (Steam Boilers) or Paragraph 34 (Water Boilers).

NOTE: IF WATER BOILER, PROCEED DIRECTLY TO Paragraph 34.

33.INSTALL STEAM TRIM AND CONTROLS, See Fig. 7 and 25.

a.Pressure Gauge is to be installed with ½” nipple and

½” x ¼” reducing coupling in ½” tapping provided in upper corner of End Section using wrench applied to square shank on back of gauge. DO NOT APPLY FORCE ON GAUGE CASE.

b.Install 67BC-2 Low Water Cut-Off or 47-2

Combination Feeder and Low Water Cut-Off in accordance with the Instructions packed with the control. ½” pipe extensions are provided and must be installed in the ½” tappings adjacent to the Pressure Gauge before the control can be mounted.

Unions are furnished with the 67BC-2 Low Water

Cut-Off for ease of installation. 1” pipe tappings have been provided in the End Sections for other types of Low Water Cut-Offs and Low Water Cut- Off & Feeder combinations. Fig. 25A illustrates the required mounting elevations for a M&M 150 and a 67M float LWCO. Figure 13C illustrates a

typical steam piping arrangement for pumped return systems.

c.

Install Gauge Glass Fittings into ends of tees used

 

to connect the 67BC-2 or 47-2 Control. If other

 

control is furnished, install Gauge Glass Fitting

 

directly into ½” pipe extensions.

d. Install Pressure Limit Controls as follows:

 

(1)

Boiler equipped with 67BC-2 Low Water Cut-

 

 

Off – Connect Pressure Limit furnished to ¼”

 

 

street ell and ¼” pigtail siphon. For installation

 

 

of second pressure limit (not furnished), bush

 

 

1½” pipe tapping in upper corner of End

 

 

Section. Connect Pressure Limit to this bushing

 

 

with ¼” pigtail siphon.

 

(2)

Boiler equipped with Low Water Cut-Off other

 

 

than (1) above or with Low Water Cut-Off

 

 

Feeder Combination – Bush 1½” pipe tapping

 

 

in upper corner of End Section and connect

 

 

Pressure Limit furnished to this bushing with

 

 

¼” pigtail siphon. For installation of second

 

 

pressure limit bush any available tapping on

 

 

opposite end section that is above normal water

 

 

line. Connect Pressure Limit to this bushing

 

 

with ¼” pigtail siphon.

 

(3)

Tighten limit controls by using wrench on hex

 

 

fitting at bottom of control.

 

(4)

The L404 Pressuretrol must be accurately

 

 

leveled for proper operation. It is level when the

 

 

leveling indicator hangs freely with its pointer

 

 

directly over the index mark inside the back

 

 

of the case. Level the controller by carefully

 

 

bending the steam trap (siphon loop).

e.

Install Pressure Safety Valve with fittings furnished,

 

into 1½” pipe tapping in upper corner of End

 

Section, see Fig. 12. DO NOT INSTALL A

 

SHUTOFF VALVE BETWEEN SAFETY VALVE

 

AND BOILER. If this boiler tapping is to be used

 

as Surface Blowoff, replace ell with tee and plug

 

open end of tee or valve off opening. Pressure

 

Safety Valve must be in leg of tee and in a vertical

 

position with handle up.

f.

Install Boiler Drain Valve and 3” x ¾” Bushing into

 

one of the two return tappings. The drain valve

 

may also be installed in return piping, but it must

 

be installed in the leg of a tee so that it is directly

 

opposite and as close as possible to the return

 

tapping. The leg of the tee must be at least 1½” pipe

 

size.

 

A Bottom Blowoff using a valve must also be

 

connected to one of the return tappings. The ¾”

 

Drain Valve may be used for Bottom Blowoff for

 

5009B or smaller boilers, since any Bottom Blowoff

 

piping or valves for 5009B or smaller boilers must

 

be at least ¾”. Bottom Blowoff piping and valves

 

for Boilers 5010B through 5021B must be at least

28

Fig. 25

STEAM TRIM AND CONTROLS

1”. Bottom Blowoff piping and valves for 5022B

Boilers and larger must be at least 1¼”.

Image 28
Contents Series 5B Section I Equipment Check List Important Information Canadian Equipment Check List Canadian Equipment Check List Dimensional Data Natural GAS Maximum 14 W.C. Minimum 5.5 W.CDo not Install this Boiler on Carpeting Provide Combustion and Ventilation AIRBASE-BURNER-MANIFOLD Assemblys Single Manifold Base 5006B Thru 5014B Section BoilersLEH Section on Base Assembly of Center Sections Dual Manifold Bases 5015B Thru 5026B Section BoilersArrangement of Sections and Canopys Open Steam or Water Trim Carton Purpose of Tappings and Their LocationsTesting Boiler Assembly for Leaks Installation of BUILT-IN HeaterConnect Supply and Return Piping to Heating System Attachment of Flue Covers Sealing of BASE, Installation Flue Covers and CanopiesOxygen Corrosion Page Page Page Page Recommended Water Boiler Piping Supply Connection & I Return ConnectionSupply Connections & 2 Return Connections Sizes 5006B Thru 5019BInstallation of Jacket Parts Common to ALL Boiler Sizes Installation of Jacket Support Brackets to Base END PanelsPage Exploded View of Jacket 6 Thru 10 Section Boilers Securing of CANOPY/DRAFTHOOD CANOPY/DRAFTHOOD Mounting Diagram Exploded View of Jacket 11 Thru 19 SECT. Boilers Completion of Jacket Installation 11 Thru 26 Section Boilers Exploded View of Jacket 20 Thru 22 SECT. Boilers Exploded View of Jacket 26 SECT. Boilers Shutoff Valve Between Safety Valve Steam Trim and ControlsMounting Elevations of M&M 150 and a 67M Float Lwco Water Trim and Controls Recommended Piping to BUILT-IN Tankless Heaters Open GAS Train CartonsOpen Gas Controls Cartons Installation of S8610M Module Pilot Piping EI Control System Robertshaw7000 A B Thru 5009BPilot Piping EI Control System V88A A B Thru 5026B NAT. GAS Canada 5006B Thru 5026B NAT. GASInstallation of Pilot Safety Switch EO Control System Installation of Pilot Safety SwitchPilot Piping EO Control System Installation of EO and EE Mounting Bracket and Controls EE Control SystemSect. and larger boilers Pilot Piping EE Control SystemInstallation of Pilot Safety Switch EOP Control System Pilot Piping EOP Control SystemEEP Control System Pilot Piping EEP Control SystemPage Venting Single Vent System Manifold Vent SystemPage Section IV Operation GeneralTable IV Water Content Condensation Control VariationsBe sure power is off when checking high voltage connections A B Thru 5009B Schematic Wiring Diagram EI Control System V88 GAS Train Sequence of OperationA B Thru 5014B Canada 5006B Thru 5014BSchematic wiring diagram 15 Thru 26 SECT. Boilers EI Control SystemSequence of Operation Page Safety Switch Circuit Pilot FailureWiring diagram 6 Thru 14 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring diagram 15 Thru 26 SECT. Boilers Operating and safety controls. Should any EE Control System Wiring diagram 15 Thru 26 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring Diagram 6 Thru 14 SECT. Boilers EOP Control System Turn on Main Power Switch. Main Power Light will light Wiring Diagram 15 Thru 26 SECT. Boilers EOP Control System Safety Switch Circuit Wiring Diagram 6 Thru 14 SECT. Boilers EEP Control System Pilot Failure Safety Switch Circuit Wiring Diagram 15 Thru 26 SECT. Boilers EEP Control System Make sure all manual resets are activated where applicable Normal Operation Sequence Page Check GAS Input Rate to Boiler Minimum Input Adjustments V8944B Combination ValveMotorized Modulating Actuator ScrewTest Ignition System Safety SHUT-OFF Device AS Follows Thermocouple Pilot System Combustion Chamber BURN-OFFSection V Service Removal of Jacket Front PanelAvoid Breathing Fiber Particulates and Dust Cleaning of Flueways LubricationPilot Locations Main Burner Flame Adjustment Pilot Flame Honeywell Q3481BPilot Flame Honeywell Q179D Pilot w/THERMOCOUPLEPilot Flame Honeywell Q179C Pilot Honeywell Q327A Pilot w/THERMOCOUPLEDo not drain water below gauge glass Base Parts JacketsSeries 5B Base Parts 5006B thru 5014B Number in in Table Relates to Corresponding NumberBase Parts Series 5B Base Parts 5015B thru 5026B 5015B 5016B 5017B 5018B 5019B 5020B 5021B 5022B 5024B 5026BBase Parts Canopy Boiler Size Quantity Part SizeIntegral Canopy Drafthoods & Sections Series 5B Section Replacement Chart Series 5B Base / Pilot Assemblies Series 5B Jackets 60413075 5007B Lower Top Panel 2 x 37-3/16 60413085 5008B 2 x 20-7/8 Complete Jackets Jackets Boiler Size Boiler Size 5006B 5008B 5009B 5014B 5015B 5016B 5017B 5026BV88A GAS Trains Canada Natural GAS only Fluid Power GAS Trains USA 100 5006B 5009B 5015B 5016B 5017B101 Diaphragm Valve LO-HI-LO GAS Train Canada Natural GAS onlyFluid Power GAS Trains Canada 102103 Ignition Module & Support Bracket EI Control System104 Pilot Safety SwitchDescription Manifold Module Support L62GB-3C 105 A. 5010B-5026B NAT. GAS Canada 5006B-5026B NAT. GAS106 Transformer & Pilot Line Regulator EO Control System107 108 109 110 111 EOP & EEP Control PanelEI Control System Pilot Assembly 1126236007 NAT. GAS 113EI GAS 6236003 NAT. GAS 114Not Available for LP Date Service Performed 115Limited Warranty 116