Burnham K50 manual Installation of Pilot Safety Switch EOP Control System

Page 38

Fig. 35

INSTALLATION OF PILOT SAFETY SWITCH

EOP CONTROL SYSTEM

Install AT72D Transformer on J-box.

Wire L62G13-3C Pilot Safety Switch to the 24V/40VA transformer and to the V88A Gas Valves using the 105ºC wire furnished, see Fig. 51 or 52. Run these wires to outside of jacket on underside of manifold and secure in this position with Wire Ties furnished to provide strain relief. Provide adequate support and strain relief for wiring outside jacket.

2.INSTALLATION OF PILOT PIPING – Attach the bracket for mounting of the J-box to the lower front corner of the Upper Jacket End Panel using two #10-32

x ½” MS and nuts. Mount junction box to bracket using #8 SMS. Install RV-12LT Regulator, (Packed in Gas Train Carton) and 1/8” tee in the ¼”

OD pilot tubing as shown in Fig. 36. Install 24V/40VA Transformer on J-box.

3.INSTALLATION OF PILOT SAFETY SWITCH AND

PILOT PIPING – Using two #10-32 x 2” MS and nuts, install the L62GB-3C pilot safety switch bracket on the manifold just to the right of the main burner with pilot. Install L62GB-3C pilot safety switch on bracket using two #10-32 x ½” MS. “IN” on pilot safety switch should be pointed in the direction of the Gas Train to which the pilot safety switch is to be connected, see Fig. 35.

Using ¼” OD aluminum tubing, connect the pilot shutoff valve installed in the manual shutoff valve in the gas train, to the inlet of the RV-12LT regulator (packed in Gas Train Carton). Regulator should be above Gas Train and near front of boiler, see Fig. 36.

Install 3/8” tee into outlet of regulator (USA boilers) and, using ¼” OD aluminum tubing, connect outlet of tee to “IN” connection on pilot safety switch, see Fig.

36.

Using ¼” OD aluminum tubing, connect the outlet of the pilot safety switch to the tubing or fitting connected to the pilot burner, see Fig. 36.

Connect Q309 thermocouple to pilot safety switch.

a.Completion of Wiring -

Connect power supply fused disconnect switch service switch, primary and secondary of Gas Valve Transformer, gas valves, and other controls – see Fig. 51 or 52 for wiring type and connections to be

Note - Pilot Piping duplicated on 15 sect. and larger boilers.

38

Fig. 36

PILOT PIPING

EOP CONTROL SYSTEM

Image 38 Contents
Series 5B Section I Equipment Check List Important Information Canadian Equipment Check List Canadian Equipment Check List Dimensional Data Natural GAS Maximum 14 W.C. Minimum 5.5 W.CDo not Install this Boiler on Carpeting Provide Combustion and Ventilation AIRBASE-BURNER-MANIFOLD Assemblys Single Manifold Base 5006B Thru 5014B Section BoilersLEH Section on Base Assembly of Center Sections Dual Manifold Bases 5015B Thru 5026B Section BoilersArrangement of Sections and Canopys Open Steam or Water Trim Carton Purpose of Tappings and Their LocationsConnect Supply and Return Piping to Heating System Installation of BUILT-IN HeaterTesting Boiler Assembly for Leaks Oxygen Corrosion Sealing of BASE, Installation Flue Covers and CanopiesAttachment of Flue Covers Page Page Page Page Supply Connections & 2 Return Connections Recommended Water Boiler PipingSupply Connection & I Return Connection Sizes 5006B Thru 5019BInstallation of Jacket Parts Common to ALL Boiler Sizes Installation of Jacket Support Brackets to Base END PanelsPage Exploded View of Jacket 6 Thru 10 Section Boilers Securing of CANOPY/DRAFTHOOD CANOPY/DRAFTHOOD Mounting Diagram Exploded View of Jacket 11 Thru 19 SECT. Boilers Completion of Jacket Installation 11 Thru 26 Section Boilers Exploded View of Jacket 20 Thru 22 SECT. Boilers Exploded View of Jacket 26 SECT. Boilers Shutoff Valve Between Safety Valve Steam Trim and ControlsMounting Elevations of M&M 150 and a 67M Float Lwco Water Trim and Controls Recommended Piping to BUILT-IN Tankless Heaters Open GAS Train CartonsOpen Gas Controls Cartons Installation of S8610M Module Pilot Piping EI Control System Robertshaw7000 A B Thru 5009B Pilot Piping EI Control System V88A A B Thru 5026B NAT. GAS Canada 5006B Thru 5026B NAT. GASPilot Piping EO Control System Installation of Pilot Safety SwitchInstallation of Pilot Safety Switch EO Control System Installation of EO and EE Mounting Bracket and Controls EE Control SystemSect. and larger boilers Pilot Piping EE Control SystemInstallation of Pilot Safety Switch EOP Control System Pilot Piping EOP Control SystemEEP Control System Pilot Piping EEP Control SystemPage Venting Single Vent System Manifold Vent SystemPage Section IV Operation GeneralTable IV Water Content Condensation Control VariationsBe sure power is off when checking high voltage connections A B Thru 5009B A B Thru 5014B Schematic Wiring Diagram EI Control System V88 GAS TrainSequence of Operation Canada 5006B Thru 5014BSchematic wiring diagram 15 Thru 26 SECT. Boilers EI Control SystemSequence of Operation Page Safety Switch Circuit Pilot FailureWiring diagram 6 Thru 14 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring diagram 15 Thru 26 SECT. Boilers Operating and safety controls. Should any EE Control System Wiring diagram 15 Thru 26 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring Diagram 6 Thru 14 SECT. Boilers EOP Control System Turn on Main Power Switch. Main Power Light will light Wiring Diagram 15 Thru 26 SECT. Boilers EOP Control System Safety Switch Circuit Wiring Diagram 6 Thru 14 SECT. Boilers EEP Control System Pilot Failure Safety Switch Circuit Wiring Diagram 15 Thru 26 SECT. Boilers EEP Control System Make sure all manual resets are activated where applicable Normal Operation Sequence Page Check GAS Input Rate to Boiler Motorized Modulating Actuator Minimum Input AdjustmentsV8944B Combination Valve ScrewTest Ignition System Safety SHUT-OFF Device AS Follows Thermocouple Pilot System Combustion Chamber BURN-OFFSection V Service Removal of Jacket Front PanelAvoid Breathing Fiber Particulates and Dust Cleaning of Flueways LubricationPilot Locations Pilot Flame Main Burner Flame AdjustmentPilot Flame Honeywell Q3481B Honeywell Q179D Pilot w/THERMOCOUPLEPilot Flame Honeywell Q179C Pilot Honeywell Q327A Pilot w/THERMOCOUPLEDo not drain water below gauge glass Base Parts JacketsSeries 5B Base Parts 5006B thru 5014B Number in in Table Relates to Corresponding NumberBase Parts Series 5B Base Parts 5015B thru 5026B 5015B 5016B 5017B 5018B 5019B 5020B 5021B 5022B 5024B 5026BBase Parts Canopy Boiler Size Quantity Part SizeIntegral Canopy Drafthoods & Sections Series 5B Section Replacement Chart Series 5B Base / Pilot Assemblies Series 5B Jackets 60413075 5007B Lower Top Panel 2 x 37-3/16 60413085 5008B 2 x 20-7/8 Complete Jackets Jackets Boiler Size Boiler Size 5006B 5008B 5009B 5014B 5015B 5016B 5017B 5026BV88A GAS Trains Canada Natural GAS only Fluid Power GAS Trains USA 100 5006B 5009B 5015B 5016B 5017B101 Diaphragm Valve LO-HI-LO GAS Train Canada Natural GAS onlyFluid Power GAS Trains Canada 102103 Ignition Module & Support Bracket EI Control SystemDescription Manifold Module Support L62GB-3C Pilot Safety Switch104 105 A. 5010B-5026B NAT. GAS Canada 5006B-5026B NAT. GAS106 Transformer & Pilot Line Regulator EO Control System107 108 109 110 111 EOP & EEP Control PanelEI Control System Pilot Assembly 112EI GAS 1136236007 NAT. GAS Not Available for LP 1146236003 NAT. GAS Date Service Performed 115Limited Warranty 116