GTO SL-2000B Wiring the Second Operator, This Step is for SL-2000/2200 Installation only

Page 37

WIRING THE SECOND OPERATOR

When the units are set in place and you have completed wiring the first unit follow the instructions below.

Step 1: With the PRO SL-1000 or SL-2000 control box open, use a screw driver to punch out the round knockout hole located on the bottom next to the First Operator power cable. Install the strain relief for the Second Operator power cable. Leave about 6” of the power cable and tighten the strain relief nut to secure the wires.

 

Relief

Lock Nut

 

 

 

Strain

Hub

 

Sealing Nut

 

 

 

Lock Nut

 

 

Hub

 

Wire From Second

Sealing Nut

 

Operator Battery

First Operator Power Cable

Second Operator Power Cable

THIS STEP IS FOR SL-2000/2200

INSTALLATION ONLY

Step 1a: Run the battery jumper wire through the PVC from the battery in the Second Operator to the battery in the First Operator. Use the side strain reliefs on the control boxes to run battery jumper wire into control boxes. Using spade connectors, con- nect positive to positive and negative

18VAC SOLAR ~ ~ – +

POWER IN

RED BLK ORG BLU GRN CLS EDG

OPN EDG

FIRST OPERATOR

 

GREEN

BLUE

ORANGE

BLACK

RED

RED BLK ORG BLU GRN CLS EDG OPN EDG

SECOND OPERATOR

GREEN

BLUE

ORANGE

BLACK

RED

SEQ1

ON

 

 

SEQ2

 

LEARN

 

 

 

GRN ORG

BLU

WHT

R

B G

 

 

 

ALARM ACCESSORY

 

RCVR

to negative.

Low Voltage Wire from AC Transformer

Step 2: Run the second power cable through PVC conduit to the Second Operator. Con- nect the wires to the motor and limit switch- es as shown in illustration

Step 3: Adjust the DIP switches on the First Operator control board for the ap- propriate dual gate settings, following the directions on next page.

 

 

 

 

 

 

Power Cable

Power Cable

from First Operator

from Second Operator

Limit Nut A

Limit Nut B

Open position stop –

Closed position stop –

if gate opens right to left.

if gate opens right to left.

Closed position stop –

Open position stop –

if gate opens left to right.

if gate opens left to right.

Limit Switches

 

BLUE (N/O contact)

 

GREEN (common)

Motor

ORANGE (N/O contact)

BLACK to Motor RED

 

 

RED to Motor BLACK

Second Operator

Power Cable

35

Image 37
Contents Automatic Gate Operator Table of Contents Important Safety Instructions Before Installation For the InstallerII. During Installation For the System DesignerIII. After Installation Secondary Means of Protection Against Entrapment Entrapment Alarm UL 325No ONE should Cross the Path of the Moving Gate For the CONSUMER/END UserPoint hazard Required Safety Precautions for GatesSL Series Moving Gate Can Cause Injury Or Death GTO PRO SL-1000 Series Technical Specifications GTO PRO SL-2000 Series Technical Specifications Parts Identification Overview of Operator Installation Single Gate Operator InstallationGate Preparation Mounting the Legs on the Slide Gate Operator Recommended Wiring and USE of ConduitProceeding to the next step Determining the Mounting Position and Mounting the OperatorBefore Pouring Concrete 1 Make sure operator is Centered between roller posts and aligned with stringTo Open the Gate Manually Installing the ChainConnecting the Battery Powering the SystemInstallation of the GTO Transformer No more than 1000 ftEstimated Maximum Number of Cycles Per Day Solar Zones and Gate ActivityStep 18VAC See Illustration KRight Control Board SettingsPotentiometers Setting the Personal Transmitter Code Run the cable through PVC conduit to protect it from damage Mounting the ReceiverIf your gate opens from Right to Left Adjusting the Limit SwitchesHowever, if your gate opens from Left to Right Counter ClockwiseConnecting Additional Safety Devices Connecting Safety DevicesWHT White Used with GRN Green Connecting AccessoriesBLU Blue Used with GRN Green ORG Orange Used with GRN GreenAttaching the Housing Maintenance Maintenance Trouble Shooting GuideConnected to these terminals System Test SpecificationsWarranty and Repair Service Limited Two Year WarrantyInstructions for the Installation Dual Slide Gate System Second Gate Auxiliary Operator Parts & Hardware Dual Gate System InstallationControl Unit Preparing the GatesThis Step is for SL-2000/2200 Installation only Wiring the Second OperatorRefer to the illustrations on the next Setting the Control Board for Dual Gate InstallationsStep Accessories #41 Slide Gate Chain RB207 Vehicular Gate Operator Class Categories When You Know Multiply By To Find SymbolInstallation of this operator conforms to Class Installation Check ListInstructions