GTO SL-1000B, SL-2000B installation manual Setting the Control Board for Dual Gate Installations

Page 38

SETTING THE CONTROL BOARD FOR DUAL GATE INSTALLATIONS

DIP SWITCHES

The Control Board DIP switches must be set to accommodate your particular type of installation. Since the SNGL / DUAL, SEQ1, and SEQ2 DIP switches are used by dual gate operator systems, they will be discussed in the following steps.

STEP 4:

Make sure the control box power switch is OFF.

STEP 5:

Unscrew and remove the control box cover. Use a small screwdriver to move the SNGL / DUAL DIP switch to DUAL (see illustration).

The order of gate operation (“sequencing”) must now be determined for your dual gate operators to function properly.

PULL/PUSH

SNGL/DUAL

SEQ1

SEQ2

 

4

 

3

ON

2

1

OBSTRUCT

SENS.

MINMAX

LEARN

Refer to the illustrations on the next page.

NOTE: The terms “FIRST OPERATOR” and “SECOND OPERATOR” refer to a unit wired to the terminal block of the same name.

STEP 6:

BOTH OPERATORS OPEN SIMULTANEOUSLY BOTH OPERATORS CLOSE SIMULTANEOUSLY

SEQ1 = ON SEQ2 = OFF

If SEQ1 is set to ON, and SEQ2 is set to OFF, the FIRST OPERATOR and SECOND OPERATOR open simultaneously, and the FIRST OPERATOR and SECOND OPERATOR close simultaneously (see illustration).

PULL/PUSH

SNGL/DUAL

SEQ1

SEQ2

 

4

 

3

ON

2

1

OBSTRUCT

SENS.

MINMAX

LEARN

36

Image 38
Contents Automatic Gate Operator Table of Contents Important Safety Instructions II. During Installation For the InstallerBefore Installation For the System DesignerIII. After Installation Entrapment Alarm UL 325 Secondary Means of Protection Against EntrapmentFor the CONSUMER/END User No ONE should Cross the Path of the Moving GateRequired Safety Precautions for Gates Point hazardSL Series Moving Gate Can Cause Injury Or Death GTO PRO SL-1000 Series Technical Specifications GTO PRO SL-2000 Series Technical Specifications Parts Identification Gate Preparation Single Gate Operator InstallationOverview of Operator Installation Recommended Wiring and USE of Conduit Mounting the Legs on the Slide Gate OperatorBefore Pouring Concrete 1 Make sure operator is Determining the Mounting Position and Mounting the OperatorProceeding to the next step Centered between roller posts and aligned with stringInstalling the Chain To Open the Gate ManuallyInstallation of the GTO Transformer Powering the SystemConnecting the Battery No more than 1000 ftSolar Zones and Gate Activity Estimated Maximum Number of Cycles Per DayStep See Illustration K 18VACControl Board Settings RightPotentiometers Setting the Personal Transmitter Code Mounting the Receiver Run the cable through PVC conduit to protect it from damageHowever, if your gate opens from Left to Right Adjusting the Limit SwitchesIf your gate opens from Right to Left Counter ClockwiseConnecting Safety Devices Connecting Additional Safety DevicesBLU Blue Used with GRN Green Connecting AccessoriesWHT White Used with GRN Green ORG Orange Used with GRN GreenAttaching the Housing Maintenance Trouble Shooting Guide MaintenanceSystem Test Specifications Connected to these terminalsLimited Two Year Warranty Warranty and Repair ServiceInstructions for the Installation Dual Slide Gate System Dual Gate System Installation Second Gate Auxiliary Operator Parts & HardwarePreparing the Gates Control UnitWiring the Second Operator This Step is for SL-2000/2200 Installation onlySetting the Control Board for Dual Gate Installations Refer to the illustrations on the nextStep Accessories #41 Slide Gate Chain RB207 When You Know Multiply By To Find Symbol Vehicular Gate Operator Class CategoriesInstructions Installation Check ListInstallation of this operator conforms to Class