is

C13 Concentric wall flue terminal specifications

Subject

 

Description

 

 

 

Wall flue terminal set:

Art. No.

0302 504 1

• 1x Wall flue terminal (incl. wall flange

 

 

Construction

Concentric

& clamping ring)

 

 

Manufacturer

Muelink & Grol

• 1x Pipe 500 mm

 

 

Type

M2000 MDV SEC

• 1x Bend 90°

 

 

 

 

 

Pipe material

Construction

Concentric

 

 

 

 

Chimney flue

Thick-walled aluminium with lip ring seal

 

 

 

 

Air supply

Thin-walled galvanised sheet steel

 

 

 

Pipe diameters

Chimney flue

Ø 100 mm

 

 

 

 

Air supply

Ø 150 mm

 

 

 

(1) No other wall flue terminal is permitted. Use this item number to order the wall conduit set from supplier, manufacturer or wholesaler.

C33 concentric roof flue terminal specifications

Subject

 

Description

 

 

 

Roof flue terminal set:

Art. No.

0304 423 1

• 1x Wall flue terminal (incl. clamping

 

 

Construction

Concentric

ring)

 

 

Manufacturer

Muelink & Grol

• 1x Pipe 1000 mm

 

 

Type

M2000 DDV HR-C

• 1x Mounting flange

 

 

 

 

 

Pipe material

Construction

Concentric

 

 

 

 

Chimney flue

Thick-walled aluminium with lip ring seal

 

 

 

 

Air supply

Thin-walled galvanised sheet steel

 

 

 

Pipe diameters

Chimney flue

Ø 100 mm

 

 

 

 

Air supply

Ø 150 mm

 

 

 

(1) No other roof flue terminal is permitted. Use this item number to order the roof conduit set from supplier,manufacturer or wholesaler.

3.9.4Parallel connections

The table states the maximum pipe lengths for parallel systems. The maximum pipe length depends on the chosen diameter.

Warning

Install flue component pipe runs with a run-off of 5 mm per metre.

Chimney flue requirements for parallel systems

 

 

 

 

 

 

 

Appliance

Diameter1

Maximum

Lequivalent

Lequivalent

 

 

total length

90° bend

bend 45°

SGE 40

 

 

 

 

 

 

 

 

 

SGE 60

100 mm

25 m

4.6 m

1.2 m

 

 

 

 

 

SGE 40

 

 

 

 

 

 

 

 

 

SGE 60

130 mm

100 m

2.4 m

1.4 m

 

 

 

 

 

1) Parallel systems with diameter of 130 mm or 150 mm. If the maximum total

length for a diameter of 130 mm is insufficient, 150 mm diameter must be

used. Any diameter enlargement must be carried out on both air supply and

chimney flue.

 

 

 

 

 

 

 

 

 

Instruction manual SGE