Install
Symbols used in this manual
Connect control wiring
Cascade XR Battery Enclosures
Safety
Total Power Off
Page 1
Image 1
Installation and
Start-Up
InfraStruXure
®
For Medium Data Centers
40 kW 208/480/600 V
Page 1
Page 2
Page 1
Image 1
Page 1
Page 2
Contents
Installation and Start-Up
About this Manual
Contents
Specifications
Symbols used in this manual
Safety
Maintenance performed while the PDU is receiving input power
Installation/Maintenance
Total Power Off
EMI
Emergency Power Off EPO
Space Considerations
Site Planning
Page
Installation Procedure Overview
Installation Procedures
See Start-Up Procedure on page 29 for detailed instructions
Tools Required
Level the PDU, UPS, NetShelter, and XR Battery Enclosures
Exchange Side Panels
Exchange Side Panels
Connect Battery Enclosure communication cables
Join the PDU, UPS, and XR Battery Enclosures
Connect Utility Conductors to the PDU
Access the PDU Main Input switch
Attach conduit to the PDU for the input conductors
Input Voltage Circuit Breaker Amperage
Install a circuit breaker
Connect input conductors
Route the input conductors to the Main Input switch
GEC
PDU
Connect AC Power and Control Wiring
Connect control wiring
Cascade XR Battery Enclosures
Connect DC Power Wiring, if Applicable
XR Battery Enclosure
Overview
Connect an Emergency Power Off Switch
Connect an EPO switch to the user connection plate
Overview
Overhead Wiring
Route and Attach Power Cables to the Racks
For single-feed devices within a
Under Floor Wiring
InfraStruXure System Installation and Start-Up
Route Data Cables to the InfraStruXure Manager Hub or Switch
Safety warnings
Apply power to the system
Heavy Use two people to lift and install power modules
Start-Up Procedure Apply power to the system
Control Menu
Verify UPS battery operation
Top-Level Menu
Start the UPS
Verify proper voltage and phase rotation at the UPS
Fuel % Load % 208V out000V 60Hz Runtime 1hr 2m
Verify bypass operation
Confirm Yes, UPS into Bypass No, Abort
Ensure that the Q2 circuit breaker on the PDU is closed on
Power the PDU Distribution Breakers
Configure the InfraStruXure Manager
Page
KW InfraStruXure PDU
Specifications