Installation Procedures: Connect Utility Conductors to the PDU

Route the input conductors to the Main Input switch

For overhead wiring, run the input conductors directly to the Main Input switch.

For wiring under a raised floor, run the input conductors through the wireway () within the PDU to the Main Input switch.

Connect input conductors

Electrical Hazard: A licensed electrician must connect input conductors to the PDU!

Torque specs and tools required. Before connecting to the terminals, verify the torque specs below by checking the specifications on the Main Input switch.

Terminal

 

Torque

Tools

 

 

 

 

L1, L2, L3

 

150 in-lb

6-mm Allen wrench

N

 

125 in-lb

13-mm socket wrench

G, GEC

 

4–6 AWG: 45 in-lb

Slotted screwdriver

 

 

8 AWG: 40 in-lb

 

 

 

 

 

Only on PDUs without a transformer.

 

 