Installation Procedures: Installation Procedure Overview
6. Connect utility conductors to the PDU.
For instructions, see “Connect Utility Conductors to the PDU” on page 14.
7. Connect AC power and control wiring.
See “Connect AC Power and Control Wiring” on page 18 for detailed instructions.
8. Connect DC power wiring, if applicable.
See “Connect DC Power Wiring, if Applicable” on page 20 for detailed instructions.
9 . Connect an EPO switch to the PDU user connection plate
See “Connect an Emergency Power Off Switch” on page 22 for detailed instructions.
10. Connect User Contact Inputs and Relay Outputs to the PDU user connection plate.
See “Connect User Input Contacts and Relay Outputs to the User Connection Plate” on page 24 for detailed instructions.
11. Install Shielding Troughs, Shielding Partitions, and Cable Ladders.
For instructions, see the manuals included with your Shielding Troughs, Shielding Partitions, and Cable Ladders.
12.Install the Rack Automatic Transfer Switches (ATS), Rack Power Distribution Units, and other InfraStruXure
For instructions, see the manuals included with your Rack ATS, Rack PDU, or other InfraStruXure
13. Route and attach power cables to each Rack ATS and/or Rack PDU.
See “Route and Attach Power Cables to the Racks” on page 25 for detailed instructions.
14. Route and attach communication cables to the InfraStruXure Manager hub (or switch).
See “Route Data Cables to the InfraStruXure Manager Hub (or Switch)” on page 28 for detailed instructions.
15.Start the system.
Only qualified,
See “Start-Up Procedure” on page 29 for detailed instructions.
8 | InfraStruXure System - Installation and |