Installation Procedures: Installation Procedure Overview

6. Connect utility conductors to the PDU.

For instructions, see “Connect Utility Conductors to the PDU” on page 14.

7. Connect AC power and control wiring.

See “Connect AC Power and Control Wiring” on page 18 for detailed instructions.

8. Connect DC power wiring, if applicable.

See “Connect DC Power Wiring, if Applicable” on page 20 for detailed instructions.

9 . Connect an EPO switch to the PDU user connection plate

See “Connect an Emergency Power Off Switch” on page 22 for detailed instructions.

10. Connect User Contact Inputs and Relay Outputs to the PDU user connection plate.

See “Connect User Input Contacts and Relay Outputs to the User Connection Plate” on page 24 for detailed instructions.

11. Install Shielding Troughs, Shielding Partitions, and Cable Ladders.

For instructions, see the manuals included with your Shielding Troughs, Shielding Partitions, and Cable Ladders.

12.Install the Rack Automatic Transfer Switches (ATS), Rack Power Distribution Units, and other InfraStruXure rack-mount devices.

For instructions, see the manuals included with your Rack ATS, Rack PDU, or other InfraStruXure rack-mount device.

13. Route and attach power cables to each Rack ATS and/or Rack PDU.

See “Route and Attach Power Cables to the Racks” on page 25 for detailed instructions.

14. Route and attach communication cables to the InfraStruXure Manager hub (or switch).

See “Route Data Cables to the InfraStruXure Manager Hub (or Switch)” on page 28 for detailed instructions.

15.Start the system.

Only qualified, APC-trained personnel may perform a system start-up.

See “Start-Up Procedure” on page 29 for detailed instructions.

8

InfraStruXure System - Installation and Start-Up

Page 12
Image 12
APC 480, 208, 600 manual See Start-Up Procedure on page 29 for detailed instructions