Start-Up Procedure: Apply power to the system
InfraStruXure System - Installation and Start-Up 37
3. Close (turn ON) the Q3 circuit breaker on the InfraStruXure
PDU.
Note: The H2 LED above the Q2 circuit breaker illuminates, indicating that it is safe to operate
the Q2 circuit breaker.
4. Open (turn OFF) the Q2 circuit breaker on the InfraStruXure
PDU.
The UPS will display a Forced Bypass message on the
display interface and the Fault LED will be red.
Note: The H2 LED above the Q2 circuit breaker illuminates, indicating that it is safe to operate
the Q2 circuit breaker.
5. Command the UPS into static bypass operation
through the UPS display interface:
a. Press the ESC key to open the top-level
menu.
b. Select Control on the top-level menu, and
press the ENTER key.
Top-Level Menu
c. Select UPS Into Bypass on the Control
menu, and press the ENTER key.
Control Menu
d. On the next screen: select Yes , UP S i nt o
Bypass, and press the ENTER key.
Confirmation Screen
Control
Status
Setup
Accessories
Logging
Display
Diags
Help
UPS Into Bypass
Do Self Test
Simulate Power Fail
Graceful Reboot
Graceful Turn Off
Start Runtime Cal
Turn Load On
Confirm
Yes, UPS into Bypass
No, Abort