Start-Up Procedure: Apply power to the system

2. Close (turn ON) the PDU distribution panel breakers.

Note: When the distribution panel circuit breakers are closed, the PDU power cables and connected equipment are energized.

Configure the InfraStruXure Manager

Once all equipment is installed, the network cables are connected to the InfraStruXure Manager hub (or switch), and start-up of the system is complete, configure the InfraStruXure Manager.

For instructions, see the InfraStruXure Manager Installation and Quick-Startmanual included with your InfraStruXure Manager.

Note: If you use PowerChute Network Shutdown (PCNS) software with your InfraStruXure UPS, your UPS must have a connection to the “User LAN” (public network) for PCNS to function correctly. If the Network Management Card installed in your UPS is connected to the InfraStruXure Manager’s “APC LAN,” you must install a second Network Management Card in your UPS and connect it to the “User LAN”

(public network) to use PCNS.