Site Planning

Space Considerations

Use the figure below to determine the space requirements for installing the InfraStruXure PDU, Symmetra PX UPS, and XR Battery Enclosure. Consult local codes and the NEC for additional requirements.

Ceiling Clearance

>304 mm/12 in

Minimum Rear Clearance

208 V: 914 mm/36 in

Minimum Front Clearance

480 V: 1067 mm/42 in

208 V 914 mm/36 in

480 V: 1067 mm/42 in

InfraStruXure System - Installation and Start-Up