Installation Procedures: Connect Utility Conductors to the PDU
At the Main Input switch, connect the input wiring according to the labels on the switch and the illustrations below.
Warning: Connect the conductors to the terminals according to the labels on the terminals. Use copper conductors only.
| 208/480/600 V input with a transformer: | G | L1L2 L3 | 
suitable grounding electrode
GEC

| 208 | V input without a transformer: | 
 | 
 | 
 | 
 | L1L2 L | 3 | |||||||
| 208 | V,  | G | 
 | |||||||||||
| 
 | 
 | 
 | 
 | |||||||||||
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
 | 