Start-Up Procedure: Apply power to the system

Verify proper voltage and phase rotation at the UPS

1. Close (turn ON) the Q1 circuit breaker on the PDU to apply power to the UPS.

2.Ensure A-B-C clockwise rotation at the UPS input terminal block, using a phase rotation meter.

3.Verify proper voltage is present at the UPS input terminal block (208V, metered phase-to-phase), using a true RMS voltmeter.

Start the UPS

1.Set the UPS DC Disconnect circuit breaker to ON, and then set the UPS System Enable switch to ON.

2.If applicable, set the XR Battery Enclosure DC Disconnect circuit breaker to ON.

When the System Enable switch is in the ON position, the Startup screen appears on the display interface of the Symmetra

PX UPS.

Then, the top-level status screen appears on the display interface. This may take up to 40 seconds.

px0013a

PowerView RM

Rev: 000 English

Please wait...

Fuel %

Load %

In 208V out000V 60Hz Runtime: 1hr 2m

34

InfraStruXure System - Installation and Start-Up

Page 38
Image 38
APC 600, 480, 208 manual Verify proper voltage and phase rotation at the UPS, Start the UPS