Start-Up Procedure: Apply power to the system

6. Close (turn ON) the Q2 circuit breaker on the InfraStruXure PDU.

Note: The H3 LED above the Q3 circuit breaker illuminates, indicating that it is safe to operate the Q3 circuit breaker.

7. Open (turn OFF) the Q3 circuit breaker on the InfraStruXure PDU.

8. Command the UPS out of static bypass operation through the UPS display interface:

a. Press the ESC key at the top-level status screen to open the top-level menu and have access to eight submenus.

b. Select Control, and press the ENTER key.

c. Select UPS Out of Bypass on the Control menu, and press the ENTER key.

On the next screen: select Yes, UPS out of Bypass, and press the ENTER key.

Power the PDU Distribution Breakers

1. Ensure that the Q2 circuit breaker on the PDU is closed (ON).

Note: When Q2 is closed, the PDU distribution panel is energized.

38

InfraStruXure System - Installation and Start-Up

Page 42
Image 42
APC 480, 208, 600 manual Power the PDU Distribution Breakers, Ensure that the Q2 circuit breaker on the PDU is closed on