Chapter 2 System Installation

2.5.2 Install 1 RU Distribution Shelf Load Connections

Figure 2-23 Installing GMT Cabling

Step 4 Connect cables to equipment that requires the supplied DC Power per that equipment’s specifications. Step 5 Install fuses by sliding them into the appropriate slot (Figure 2-24).

Figure 2-24

Installing Fuses

Blank

15A Fuse

Blank

124771

Note An empty space should be left on each side of any 15A GMT fuse used for thermal considerations.

2.5.2 Install 1 RU Distribution Shelf Load Connections

The following section is for systems that use the 1 RU Distribution Shelf. For systems without the 1 RU Distribution Shelf, go to Chapter 4, “System Operation.”