World Class 3000
Instruction Manual
QUICK START GUIDE FOR IFT 3000 SYSTEMS
Before using the Quick Start Guide, please read “WHAT YOU NEED TO KNOW BEFORE INSTALLING AND WIRING A ROSEMOUNT IFT 3000 INTELLIGENT FIELD TRANSMIT- TER WITH WORLD CLASS 3000 PROBE” on the preceding page.
1.Install the probe in an appropriate location on the stack or duct. Refer to Section 2, para- graph
2.Connect calibration gas and reference air to the probe.
3.Verify the jumper selection on the IFT 3000 power supply board, microprocessor board, and interconnect board, as shown in Figure 2.
4.Install the IFT 3000 in the desired location. Refer to Section 2, paragraph
5.Wire the probe to the IFT as shown in Figure 2.
6.Connect line voltage to the IFT as shown in Figure 2.
7.Apply power to the IFT 3000. Allow sufficient time for the probe to reach normal operating temperature. The time required will vary based on process temperature and other variables.
8.Perform a manual (semiautomatic) calibration. Press the CAL key on the GUI. Select the PERFORM CALIBRATION
Rosemount Analytical Inc. A Division of Emerson Process Management |