24G SERIES FLATBOTTOM GAS FRYERS CHAPTER 3: INSTALLATION INSTRUCTIONS
3.7 Gas Conversion Procedures (cont.)
CE UNITS ONLY:
When converting from G20 to G25 gas, the following procedures apply:
♦Equipment replacement is not required.
♦Adjust orifice gas pressure to the appropriate value listed in the table on page
♦After adjustment, replace the
When converting from G20 (or G25) gas to propane/LP G31 (or
♦Burner orifices and pilot orifice MUST be replaced.
♦Adjust orifice gas pressure to the appropriate value listed in the table on page
♦After adjustment, replace the
♦Factory MUST be notified so the conversion can be documented and a new rating plate can be sent out.
When converting from G20 (20 mbar) to G25 (25 mbar), or
♦Check
♦Other adjustments are not necessary.
Conversion from one gas family to another (i.e. changing from natural gas to propane) requires special components. Obtain the necessary components using the
Conversions can only be executed by qualified,