Hardware installation | Rack installation/removal of server |
4.2Rack installation/removal of server
VCAUTION!
●Follow the safety instructions and the rack installation instructions in chapter “Important information” on page 23.
●At least two people are needed to position the server into/out of the rack.
●The rack may tip over if more than one unit is removed at the same time.
Rack requirements
The rack systems from Fujitsu Siemens Computers (PRIMECENTER Rack, DataCenter Rack) ideally support installation of PRIMERGY server systems. Installation in the currently standard rack systems of various manufacturers (3rd party rack) is possible in so far as they support the
IThe Classic Rack is not supported for the PRIMERGY RX600 S4.
To accommodate the ventilation concept and ensure proper ventilation, any unused areas in the rack must be sealed using dummy covers.
The power is supplied via the multiple socket outlets fitted in the rack.
The main features of the rack systems from Fujitsu Siemens Computers are as follows:
PRIMECENTER Rack
–In connection with
Two of these assembly brackets and/or the sliding rails are provided with a linear alignment possibility to ensure also an adjustment to different rack depths.
–Enhanced cable management in the lateral rack area.