5.When the test is completed the screen shows the results of the test.

 

 

 

 

Options

 

 

 

 

 

 

 

 

 

 

Test

 

 

 

 

 

1.

Login

 

 

 

 

 

 

 

 

 

 

 

 

 

.

Logout

 

 

 

 

 

Communication Unit

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

CPU1 165-0086-100

ROM OK

RAM OK

DP-RAM OK

Viterbi OK

Press any key to escape.

CPU2 165-0087-103

ROM OK

RAM1 OK

RAM2 OK

EEPROM OK

GPS OK

DP-RAM OK

Figure 8-2 Sample communication unit self test results

Either “OK” or “NG” (No Good) appears next to each ROM and RAM tested. NG display releases the audible alarm. For defec- tive ROM, RAM, DP-RAM, EEPROM or VITERBI replace the CPU Board. For GPS, NG appears when there is no GPS board or it is faulty.

6. Press any key to finish the communication unit test.

Performance Verification (PV) Test

After the FELCOM 12 is installed, the installing technician usually confirms that the unit is functioning properly and is logged in with the Inamarsat C system by conducting the PV test.

The PV test consists of the message reception test, message transmis- sion test and distress alert test.

The results of the test appear on the PV test result display.

Note that the test cannot be conducted from a 2nd DTE. Note also that the test can be initiated by a LES.

PV test sequence

1.Select PV Test on the Test menu.

2.The NCS acknowledges request for testing.

3.The MES, upon receiving acknowledgment from NCS, goes into pending state.

4.NCS will select a (not busy) LES to perform the test.

5.The LES transmits a test message to the MES.

6.MES transmits a test message to the designated LES.

7.LES receives test message.

8-4