SCHEDULE Action
Routine
The SCHEDULE Action Routine schedules another Action Routine to be performed now, or at some later date or time.
Format: | SCHEDULE |
Resource Required: | None |
Parameters: | Date or Time: |
∙Date or "AM" (optional) - Either a date in the format mm/dd/yy, or a number of days from today. If specified as a number of days, the Time parameter must also be included.
If "AM" is specified, and the current time is greater than the "Start of Overnight Period" in the system parameters, the call is scheduled for the "AM Report Time." If the current time is between the AM Report Time and the Start of Overnight Period, then the action is scheduled for now.
If "AM" is specified, omit the Time parameter.
If Date is omitted, action is scheduled for this day.
∙Time (optional)
Either a time in the format hh:mm, or a number of minutes from the current time.
Event associated with action to be scheduled: - Name of Action Routine to be scheduled.
Action Routine Parameters: - Parameters to be passed to
scheduled Action Routine.