Installing Disk 5 (all servers)

Copyright © 2006 Nortel Networks

Installing Disk 5 (all servers)

Approximate time estimate is 30 minutes.

Procedure 17 Installing CD5

At the management pc,

1Place CD5 in the CD-ROM drive, on the server, and press Enter at the prompt.

Note 1: CD5 will eject from the CD-ROM when installed.

Note 2: For Management/Accounting servers, you will be prompted for CD6. Refer to Installing Disk 6 (MgmtSvr/AcctMgr only) on page 67 for instructions.

Application/IPCM servers (AppSvr/IPCM) will reboot.

2

ATTENTION

On a brand-new machine, only the A/LOM port is available until after CD5 completes. Once CD5 has completed, log out of the A/LOM port.

Log back in through the terminal server to the B/Serial port for the rest of the installation.

For installations on machines that have already had a system installed, just remain on the B/Serial port.

After the AppSvr/IPCM reboot, log into these servers (using the B/Serial port) and change the passwords for the sysadmin, root, and nortel users.

Change the passwords on the MgmtSvr/AcctMgr server after

CD6 (not CD5).