4. Run Cable for System
4.1Run Cables to Base Station Locations
The Base Station locations should be designated on the building floor plans provided to the installer. Base Stations can be mounted easily on raised or acoustical ceiling tiles, or on the wall. Avoid locating Base Stations in high or
Wire Specifications
The customer's wire contractor is responsible for adhering to all local codes
!for wiring.
SpectraLink recommends
Power | Max Cable Feet | Max Cable | Max Cable |
Pairs | 22 AWG | Feet | Feet |
|
| 24 AWG | 26 AWG |
|
|
|
|
1 | 1,100 | 750 | 470 |
|
|
|
|
2 | 2,200 | 1,500 | 940 |
|
|
|
|
3 | 2,200 | 2,200 | 1,400 |
|
|
|
|
!One additional pair is required for Data.
Attenuation must not exceed 6.8 dB/1,000 feet @ 772KHz.
Wire that is already installed (spare house cable) can be used when it is available. House cable will usually run from the MDF in the telephone equipment room to Intermediate Distribution Frames (IDFs) spread throughout the facility. Install new wire from the closest IDF to the Base Station. Be sure no bridge taps, multiples, or “Y” connections are created or present.
Determine the amount of wire needed to connect the Base Station to the MCU by scaling from a floor plan or a sketch, pacing, measuring, or estimating. Remember to include enough wire to reach the ceiling.
!2,200 cable feet.
Install an extra 25 feet of wire at the Base Station to allow for possible relocation.The wire length between the MCU and each Base Station may not exceed