MODEL C24EA - ELECTRICAL OPERATION
Solenoid (4SOL), Slow Fill | Primary fill for Basic machines and secondary fill for |
| Professional machines. Energized as necessary during |
| operation to replenish water in generator tank. |
Solenoid (5SOL), Vacuum Relief | Provides open air line for vacuum relief during drain cycle to |
| prevent cooking chamber flex. |
Switch (1S), Power | Rocker switch on Professional machines and linkage activated |
| plunger switch on Basic machines. Two position switch that |
| controls machine steam and drain operations. |
Switch (2S), Door | Plunger activated, switch is wired in series with timer. When |
| switch is closed and timer is set to a time or constant, regulating |
| contactor will be energized 100% of the time once ready light is |
| on (hold thermostat satisfied). |
Switch (1PAS), Pressure | Pressure |
| Cuts off electrical energy to controls circuit if pressure is above |
| set pressure. |
Thermostat (1TAS), Condensate | Monitors temperature of water entering the facility drain system. |
| Controls the cooling solenoid during cooking operation and the |
| cooling and flush solenoids during drain cycle (135E F |
Thermostat (2TAS), | Protects against heating element |
| caused by tank boiling dry. Capillary style device. Bulb is |
| mounted directly to the heating element and body is bracket |
| mounted to frame rail (257E F |
Thermostat (3TAS), Hold | Controls temperature of water in steam generator tank to 195EF |
| (closes at 195E F). |
Timer (1TR) | Used for timed cook cycles from 0 to 60 minutes. Professional |
| models have a CONSTANT position for continuous steam |
| operation. |
Transformer (1T), Main . . . . . . . . . . . . . . . . . .
Transformer (2T), Drain . . . . . . . . . . . . . . . . .
Step down transformer from line voltage to control voltage level (120VAC).
(Professional models only) Provides 24VAC for motorized drain valve during drain cycle.
Page 37 of 52 |
| F25213 (May 2006) |
|