18 | Chapter 3 Electrical Installation |
6.Connect the system output cables between the output busbars
Warning
If the load equipment will not be ready to accept power on the arrival of the commissioning engineer then ensure that the system output cables are safely isolated at their ends.
UPS Battery Connections
7.Connect the battery cables between the UPS terminals
Warning
Do not close the BCB before the equipment has been commissioned.
8. Refit the lower protective cover.
Note: For split bypass operation, ensure that the busbars ( *) between the bypass input and rectifier input are removed.
Auxiliary
terminal block
X3
|
| Q1 |
|
|
| Q2 |
|
|
| Q5 |
|
|
|
|
|
| * |
|
|
|
| Q3 |
|
|
|
|
|
|
| * |
|
|
|
|
|
|
|
|
|
|
|
| * |
|
|
|
|
|
|
|
|
| U1 | V1 | W1 | N1 | U2 | V2 | W2 | N2 | N3 | U3 | V3 | W3 |
Battery | Rectifier |
| Bypass | Earth | Output | |||||||
connections | connections | connections | connections |
Figure 3-2 Power cable connections for 160/200kVA UPS
HIPULSE U UPS Single Module And “1+N” (Expandable) 160/200/300/400kVA User Manual