g
Digital Energy™ LP Series
4.5.1.2Installation procedure:
input voltage 120Vac (optional,
If a battery extension pack is to be installed, please proceed with section 4.5.5.
If 2, 3 or 4 parallel operating units will be installed, please proceed with section 4.5.6. The numbers between (brackets) refer to figure 19 and 20 in section 5.1.
2
4
5
BATTERY
DISCONNECTED
EMERGENCY
SHUTDOWN
67
see
8 9 | see 4.5.6 / 7.3 |
Figure 7. LP 5/6-11U:
Installation procedure 120V input
1.Mount the levellers: position A to fix the UPS to the floor, position B to lift the castors from the floor. Please refer to figure 6, step 1.
2.Loosen the screws and remove the conduit boxes (17, 2x) and the cover plate (11).
3.Make sure that all circuit breakers
4.Input/output connection:
Lead the input/output cables through the cable inlet. If the cables come from below (recommended for 8kVA and 10kVA models), you can rotate the cable inlet 90 degrees. Connect the input wires to the input terminals (11b). Connect the output wires to the output terminals (11a). Please refer to section 4.5.2.2 (input) and 4.5.3 (output) for detailed information.
5.
6.An emergency shutdown switch can be connected to connector J3 on the RS232/Contact Interface Card, between pins 3 and 4. See section 6.2 for more information.
7.For advanced communication possibilities, the RS232/contact interface port (12a) can be connected to a computer system. See section 6.1 for more information.
8.The middle ‘option slot’ (13) allows easy installation of
9.The right ‘option slot’ (14) allows easy installation of the
10.Connect the utility power to the UPS.
11.If hardware modifications were necessary in step 4 because the output voltage is different from the default (208Vac), software modifications should be performed as well. Proceed with 4.5.4.
12.For a quick start proceed with section 5.2
LX: OPM_LPU_11U_5K0_10K_1US_V030 | 12 | GE DE LP 11U UPS: Installation / User Manual 3.0 (US) |