g
Digital Energy™ LP Series
5.The right option slot (14) at the rear of the unit contains the the
2 or 3. Start with 0 for the first unit, 1 for the second, 2 for the third and 3 for the last unit:
-loosen the screws, remove the
-set the dipswitch to the appointed number (fig. 18)
-
Do NOT install the network cables between the
Figure 18. Appointing a unique number to each UPS in the system
6.In the UPS many parameters can be set. It is advised to keep the same setting for each parameter in each UPS in the parallel system. In any case the following parameters are critical and should have equal settings:
-autorestart (on/off, see 5.3.3)
-output voltage (120/208/220/230/240 Vac, see 5.3.4)
-output frequency (50/60 Hz, see 5.3.4)
It is absolutely required that these parameters are set to the same value. Off factory this is the case. If you’re not sure that the units have equal settings:
-be sure that the
-be sure that utility power is connected to the UPS
-start each unit individually (see 5.2), check / change the parameters, and switch the unit off again.
7.Interconnect the
4.5.6.2 Notes concerning starting up the parallel system
For starting up the system please refer to section 5.2.
After switching on all units the LP UPSs will show the following display:
AUTORESTART OFF
PRESS ENTER
After pressing the ‘Enter/Reset’ button on one of the units the system will start up. All units will display the standard screen. The number in the lower right corner indicates the number of the UPS in the system.
LP |
|
LOAD 40% | 2 |
If the parameters mentioned in 4.5.6.1 step 6 are not set to the same value the UPS will display the following screen after
AUTORESTART OFF
SETTING MISMATCH
In this case check and correct the setting of the parameters as mentioned in 4.5.6.1, step 6.