g
Digital Energy™ LP Series
5.2Start-up
The numbers between (brackets) refer to figure 19 in section 5.1.
Note: the UPS can be started on battery power if the utility input voltage is not available or if circuit
breaker ‘utility’ is in
1.Turn breaker 'utility' (8) and breaker 'bypass' (9), both on the rear panel, into position ‘on’ (up).
2.Some UPS parameters (e.g. voltage, frequency, LCD language) are user selectable. If you want to change one or more settings, please refer to section 5.3.4
3.Turn switch 'UPS on/off' (rear panel, 7) into position ‘on’ (up). The green LED 'operation' (front panel, 5) will illuminate.
After switching on the UPS performs a
SELFTEST
IN PROGRESS
After completion of the
LP 5-11U
LOAD 37%
In case of a system failure the
4.Though the batteries (the internal energy reserve) were fully charged when the UPS left the factory, they might have lost some energy during transport and/or storage. It is recommended to allow the UPS to recharge the batteries for a few hours. This way you ensure that the UPS can provide sufficient runtime in case of a utility power failure.
5.If not yet switched on, the equipment connected to the UPS can be switched on now; operate as usual.
LX: OPM_LPU_11U_5K0_10K_1US_V030 | 24 | GE DE LP 11U UPS: Installation / User Manual 3.0 (US) |