Digital EnergyLP Series

5.4.3 Deep Battery Test

The runtime as shown on the LCD screen is calculated, and the value is initially based on the capacity of new batteries. As batteries age, their capacity deteriorates, and as a result the initial battery capacity may be too unreliable for a proper runtime prediction. The UPS is able to keep track of the aging process, if a 'deep battery test' (battery calibration test) is executed regularly. During such a test the condition of the batteries is tested, and the result of the test is stored, and used by the UPS system for future runtime calculations.

We advise performing a deep battery test on a regular basis. For accuracy reasons the interval should depend on the number of discharges . With one discharge per month a 6 month interval is sufficient. If the discharge interval is shorter than once a week a monthly deep battery test is advised.

A deep battery test can be started only if the following conditions are met:

-The load should be more than 30% of nominal load

-The batteries should be fully charged (100% on screen)

-There are no alarms at the time the test is started.

Procedure:

From the standard menu first enter the service menu (press the 'down' and 'Enter/Reset' keys simultaneously for 2 seconds). Subsequently press the 'down' key until the following screen appears:

CALIBRATE BAT press DOWN+ENTER

Press the keys ‘down’ (2) + 'Enter/Reset' (3) simultaneously, for at least 1 second.

The following screen appears:

CALIBRATE BAT

TEST ACTIVATED

The test is executed, this may take a few minutes with standard battery and full load. Partial load and/or batt. extension packs can lengthen the test period considerably. Do not change the load during the test, i.e. do not switch off or on connected equipment!

The deep battery test discharges the batteries to 'battery low' alarm level (see section 5.3.2 'battery low'). Please note that immediately after a deep battery test the expected run time is very short: allow the UPS to recharge its batteries.

After the test the second line informs about the result:

TEST SUCCESFUL

=

The test has been completed successfully

TEST FAILED

=

The test could not be executed properly: not all test conditions were fulfilled.

 

 

The UPS system was not informed about the actual battery condition!

LX: OPM_LPU_11U_5K0_10K_1US_V030

32

GE DE LP 11U UPS: Installation / User Manual 3.0 (US)

Image 34
Contents Digital Energy LP 11U Page Digital Energy LP Series Important Safety Instructions Interfacing Features Installation Important Safety InstructionsGeneral Storage BatteriesIntroduction WarrantyDescription Functional Explanation Principles of OperationAutomatic Bypass Switch Transport Unpacking InstallationPackage Contents LocationOutput voltage UPS model 120V 208V 240V Utility voltage UPS model 120V 208V 240VUPS model Tightening torque force LP 5/68/10-11U Standard installation procedure LP 5/6-11U Installation procedure 120V input Input voltage 208 or 240Vac Bypass tap factory setting 208 VoltAvailable input voltages hardware modifications Bypass tap changed to 240 VoltAvailable output voltages hardware modifications Input voltage 120Vac optional, 5/6kVA onlyOutput voltage 208Vac Output voltage 120Vac split-phase LP 5/6/8/10-11U Output tap changeOutput voltage 120Vac single phase Output voltage 220/230/240VacInput Voltage Change to Setup ScreensInput Voltage Output VoltageLP 5/6/8/10-11U Installation of battery pack Installation of parallel operating LP-U UPSs Autorestart OFF Setting Mismatch Autorestart OFF Press EnterNo-load shutdown MaintenanceECO-mode Manual bypassOperation Description of Front and Rear PanelRear panel of the step-up transformer Rear panel Step-up transformerStart-up Selftest ProgressInput Line Battery 23CUse Autonomy Time Left Operating Time 0YEAR 29DAYSStatus and Alarm Menu On Line Alarm Press UPTemp TOO High Battery Depleted Battery Charger no Float Capacitor C1 Capacity LOWInverter OFF Input and Output not Synchronized Service ScreensService Menu Software Version R2.9 FAN Speed INV.DC +Automatic Bypass Enabled Tstamp Q4Frequency Range 2% PLL Lock Speed Normal Language English Input Voltage Output VoltageOutput Frequency FAN CurveQuick Battery Test Start Automatic Bypass Enabled Service Warning DisabledTest Screens Procedure Deep Battery TestCalibrate BAT Test Activated Shutdown Other FeaturesOverload protection in bypass mode Utility startAuto Restart OFF Press Enter Superior Battery ManagementECO Auto restartEmergency shutdown Interfacing FeaturesRS232 / contact interface Relay Card optional Snmp Interface optionalPlug-in Cards Optional FeaturesExtended Runtime RPA-Facility Redundant Parallel ArchitecturePDM Power Distribution Module Seismic anchorsRecycling the UPS at the end of service life MaintenanceSafety Cooling fanSelftest Failure Temp TOO High TroubleshootingSelftest Failure Q4 not OK Specifications UPS Type 11U 10-11UAutomatic Bypass Switch Enclosure Dimensions Conduit Box Center of GravityLP 5/6/8/10-11U installation drawings LP 5/6/8/10-11U 208-240V input LP 5/6-11U 120V input