GE LP11U user manual Specifications, UPS Type 11U 10-11U

Page 42

g

Digital EnergyLP Series

10 - Specifications

UPS Type

 

:

5-11U

 

6-11U

8-11U

10-11U

Output power (kVA/kW)

 

:

5/4

 

6/4.8

8/6.4

10/8

AC input voltage

 

: 120/208/240 Vac (120V only with step-up transformer for LP 5/6-11U)

Input frequency

 

:

60/50 Hz

 

 

 

AC output voltage

 

:

120/208/220/230/240V

 

 

Output frequency

 

: 60 or 50 Hz, std. 60 Hz; selectable on front

System efficiency (full load)

 

:

87%

 

 

 

 

Line input breaker (C-type)

 

:

32A

 

32A

50A

63A

Bypass input breaker (C-type)

 

:

32A

 

32A

50A

63A

Battery safety fuse (F4A)

 

:

30A

 

30A

30A

30A

Battery safety fuse (F4B)

 

:

30A (spare)

30A (spare)

30A

30A

Internal safety fuse (F5A)

 

:

-

 

-

30A

30A

Internal safety fuse (F5B)

 

:

30A

 

30A

30A

30A

Input/output connectors

 

: terminals at rear of unit

 

 

INPUT

 

 

 

 

 

 

 

 

AC input voltage range (208V-240V)

 

 

 

 

 

 

 

at 100% load

 

:

162 - 285 V

 

 

 

at

50% load

 

:

146 - 285 V

 

 

 

at

20% load

 

:

133 - 285 V

 

 

 

AC input voltage range (120V, L5/6-11U)

 

 

 

 

 

 

at 100% load

 

:

81 - 141 V

 

 

 

at

50% load

 

:

72 - 141 V

 

 

 

at

20% load

 

:

66 - 141 V

 

 

 

Input frequency range

 

:

40-70 Hz

 

 

 

Input current wave form

 

:

sinusoidal

 

 

 

Input power factor

 

:

0.99

 

 

 

 

Max. input current at 100% load

120V

:

43.3A

 

50.8A

n.a.

n.a.

 

 

208V

:

25.0A

 

30.0A

40.5

50.3

 

 

240V

:

21.4A

 

25.1

34.8

42.0

Inrush current

 

:

none

 

 

 

 

Rectified DC voltage out

 

:

380 V

 

 

 

 

BATTERY CHARGER

 

 

 

 

 

 

 

Characteristic

 

:

U/I-characteristic, constant

current

charging until boost/float voltage, then

 

 

 

 

constant voltage charging and boost charge mode for fast recharging of

 

 

 

 

batteries

 

 

 

DC input voltage range

 

:

350-450 V

 

 

 

DC output voltage at 20 °C

 

:

float: 273 V

boost: 295 V

 

 

Output current limit (Adc)

 

:

2.0

 

2.0

3.0

3.0

OUTPUT CONVERTER

 

 

 

 

 

 

 

Output power at pf. = 0.8, VA*

 

:

5000

 

6000

8000

10000

Semiconductor

 

:

IGBT

 

 

 

 

AC output voltage

 

: 120/208/240V ± 1% static resistive load

 

 

 

 

120/208/240V ± 2% measured crest load 2.5:1

 

 

 

 

120/208/240V ± 2% dynamic mean deviation over one half cycle for 100% of

 

 

 

 

rated load applied or removed

 

Typical overload

 

:

110%

20 minutes

 

 

(temp. dependent)

 

 

130%

3.5 minutes

 

 

 

 

 

 

150%

2 minutes

 

 

Output frequency

 

: 60 or 50 Hz selectable, ± 0.1%, unless synchronized with the utility

Freq. tracking range

 

: ± 2/4/6% of nominal, user selectable

 

Output wave form

 

:

sine wave

 

 

 

Max. phase difference input-output

 

:

max 7°

 

 

 

 

Harmonic distortion

 

: 2% max. with linear load

 

 

Power factor range

 

:

Any lagging or leading power factor permitted within the specified rating to

 

 

 

 

pf. 0.5

 

 

 

 

Output derating altitude

 

: Till 1000m no derating

 

 

 

 

 

 

Above 1000m 12.5% per 1000m, max. 4000m

Protection

 

: Automatic shut down (or transfer to bypass, if bypass is available) in case of

-low/high DC voltage

-overtemperature

-overload / short circuit

The output is protected against connection to the utility supply * according to EN 50091-1

LX: OPM_LPU_11U_5K0_10K_1US_V030

40

GE DE LP 11U UPS: Installation / User Manual 3.0 (US)

Image 42
Contents Digital Energy LP 11U Page Digital Energy LP Series Important Safety Instructions Interfacing Features Important Safety Instructions InstallationGeneral Storage BatteriesWarranty IntroductionDescription Functional Explanation Principles of OperationAutomatic Bypass Switch Transport Unpacking InstallationPackage Contents LocationUtility voltage UPS model 120V 208V 240V Output voltage UPS model 120V 208V 240VUPS model Tightening torque force LP 5/68/10-11U Standard installation procedure LP 5/6-11U Installation procedure 120V input Input voltage 208 or 240Vac Bypass tap factory setting 208 VoltAvailable input voltages hardware modifications Bypass tap changed to 240 VoltInput voltage 120Vac optional, 5/6kVA only Available output voltages hardware modificationsOutput voltage 208Vac Output voltage 120Vac split-phase LP 5/6/8/10-11U Output tap changeOutput voltage 120Vac single phase Output voltage 220/230/240VacInput Voltage Change to Setup ScreensInput Voltage Output VoltageLP 5/6/8/10-11U Installation of battery pack Installation of parallel operating LP-U UPSs Autorestart OFF Setting Mismatch Autorestart OFF Press EnterNo-load shutdown MaintenanceECO-mode Manual bypassOperation Description of Front and Rear PanelRear panel of the step-up transformer Rear panel Step-up transformerStart-up Selftest ProgressInput Line Battery 23CUse Autonomy Time Left Operating Time 0YEAR 29DAYSOn Line Alarm Press UP Status and Alarm MenuTemp TOO High Battery Charger no Float Capacitor C1 Capacity LOW Battery DepletedInverter OFF Input and Output not Synchronized Service ScreensService Menu Software Version R2.9 FAN Speed INV.DC +Automatic Bypass Enabled Tstamp Q4Frequency Range 2% PLL Lock Speed Normal Language English Input Voltage Output VoltageOutput Frequency FAN CurveAutomatic Bypass Enabled Service Warning Disabled Quick Battery Test StartTest Screens Deep Battery Test ProcedureCalibrate BAT Test Activated Shutdown Other FeaturesOverload protection in bypass mode Utility startAuto Restart OFF Press Enter Superior Battery ManagementECO Auto restartEmergency shutdown Interfacing FeaturesRS232 / contact interface Relay Card optional Snmp Interface optionalPlug-in Cards Optional FeaturesExtended Runtime RPA-Facility Redundant Parallel ArchitecturePDM Power Distribution Module Seismic anchorsRecycling the UPS at the end of service life MaintenanceSafety Cooling fanTroubleshooting Selftest Failure Temp TOO HighSelftest Failure Q4 not OK Specifications UPS Type 11U 10-11UAutomatic Bypass Switch Enclosure Dimensions Conduit Box Center of GravityLP 5/6/8/10-11U installation drawings LP 5/6/8/10-11U 208-240V input LP 5/6-11U 120V input