Shipping and Receiving

Shipping

Rack assemblies are shipped in corrugated boxes. Battery cables, battery boots, terminal blocks, and labels are also included in the shipment. Each pallet can support a maximum of two (2) units. Boxes are shrink-wrapped to the pallet for added stability.

Batteries are shipped separately, and shrink wrapped to their pallet as well.

Receiving

Check for damages.

1.Upon receipt, inspect the boxes for obvious signs of rough handling.

2.Remove shrink wrap, open boxes, and conduct an internal inspection of the equipment. Keep boxes on pallet for transportation to installation site.

3.Record any damages and call the carrier immediately to allow their personnel to conduct an equipment inspection.

DO NOT contact APC first—notify the carrier instead. Otherwise, APC may be unable to assist in recovering the realized amount of the claim.

All damage claims should be as specific as possible. Information pertaining to the shipment should appear on the shipping label and related paperwork.

BE SURE to request a copy of the carrier’s inspection report!

Check for discrepancies. Make certain the shipment has arrived in its entirety. Compare information from the shipping label/parts list against what has been received. If any part is missing or might have been damaged prior to shipping, contact APC immediately.

4

Battery Rack Assembly and Installation Manual

Image 10
Contents Battery Racks for 400kW-1MW UPS Systems Assembly and Installation ManualBattery Rack Assembly and Installation Manual Contents Rack Assembly Appendix C Employing Sidecars Battery Rack Assembly and Installation Manual Safety warnings SafetySafety precautions Additional considerations Rack/battery options SpecificationsWeights and dimensions Shipping Shipping and ReceivingReceiving Positioning PlacementHandling Installation equipment Installation SiteInstallation considerations Torque specificationsParts List APC P/NBattery Cabling Rack Assembly Assembling the bottom sectionRefer to graphic in below Assembling the top section Top Side Subassembly #2 870-1657A Bottom Side Subassembly #2 Top Side Subassembly #1 Cross Bar #6 Top Side Subassembly #2 Connection Stabilizing the rack Anchoring the rack optional Accessing your wiring diagramsNumbering the batteries Positioning rails on shelves Addressing the bottom shelfWiring the batteries Rack Assembly Stud Terminal Addressing the third shelf Addressing the second shelfAddressing the top shelf Shelf-to-shelf wiring Assembling the second rack Labelling the terminal blocks Employing sidecars to support separated racksConnecting terminal blocks to battery breakers To Battery Breaker #1 BAT 1- terminal Connecting terminal blocks to batteries Rack #1, Top Shelf Terminal Block #1 Shelf-to-shelf From Battery #24 Rack #2, Top Shelf Terminal Block #2 Shelf-to-shelf From Battery #56 Applying warning labels Reattaching terminal block coversGrounding the racks Glossary APCAppendix a Battery Wiring Style E Style E, rack #1, shelf #1 topStyle E, rack #1, shelf #2 Style E, rack #1, shelf #3 Style E, rack #1, shelf #4 bottom Style E, rack #2, shelf #1 top Style E, rack #2, shelf #2 Style E, rack #2, shelf #3 Style E, rack #2, shelf #4 bottom References for Power battery cables Appendix B Battery Cabling KitsReferences for Fiamm battery cables Appendix C Employing Sidecars Sidecar overviewPositioning and accessing the sidecar Connecting terminal blocks to sidecars To BAT To BAT 2+ Appendix C Employing Sidecars Connecting sidecars to battery breakers At the SidecarBAT 2+ Top BAT BAT 1+ Top Battery Rack Assembly and Installation Manual Battery Rack Assembly and Installation Manual Battery Rack Assembly and Installation Manual APC Warranty on Batteries 990-4194A APC Worldwide Customer Support03/2004