American Power Conversion 400kW1MW installation manual Shelf-to-shelf wiring

Page 29

Rack Assembly

3.Using a rated lifting device, load batteries onto TOP shelf rails in accordance with your wiring diagram. Take note of where each numbered battery should be placed, and the proper positioning of its positive and negative terminals.

Refer to step 3 on page 18 for similar procedure.

4.Make all specified TOP shelf battery-to-battery and row-to-row connections. Refer to “Wiring the batteries” on page 18.

Shelf-to-shelf wiring

Shelf-to-shelf wiring takes place after ALL of the shelves in your rack have been fully assembled and their batteries wired together in numerical sequence. Start with the top shelf and work down.

Review “Safety” on page 1 for safety warnings and caution notices. Take heed of all safety information before proceeding with battery connections. Failure to

Warning comply could result in serious injury or death!

Using the supplied shelf-to-shelf cable, connect the HIGHEST-numbered battery on the TOP shelf to the LOWEST-numbered battery on the SECOND shelf. Then connect the highest-numbered battery on the second shelf to the lowest-numbered battery on the third shelf. Finally, connect the highest- numbered battery on the third shelf to the lowest-numbered battery on the fourth shelf.

Prior to connecting batteries, use a voltmeter to check the voltage between those terminals being connected. Any reading other than zero is unacceptable.

Note

Follow these steps for each shelf-to-shelf connection:

1.Refer to your wiring diagrams for proper cabling and termination points.

2.Before making connections, apply two (2) cable boots.

3.Connect one cable end to the open negative (-) terminal on the last battery in the upper shelf. Snap cable boot over the connected lug/terminal.

4.Apply a “protective” boot (not supplied) to the other cable end, then snake the cable downward through (space in) centrally located rails.

Boot Your Cable!!!

Battery Rack Assembly and Installation Manual

23

Image 29
Contents Assembly and Installation Manual Battery Racks for 400kW-1MW UPS SystemsBattery Rack Assembly and Installation Manual Contents Rack Assembly Appendix C Employing Sidecars Battery Rack Assembly and Installation Manual Safety precautions SafetySafety warnings Additional considerations Weights and dimensions SpecificationsRack/battery options Receiving Shipping and ReceivingShipping Handling PlacementPositioning Installation considerations Installation SiteInstallation equipment Torque specificationsAPC P/N Parts ListBattery Cabling Assembling the bottom section Rack AssemblyRefer to graphic in below Assembling the top section Top Side Subassembly #2 870-1657A Bottom Side Subassembly #2 Top Side Subassembly #1 Cross Bar #6 Top Side Subassembly #2 Connection Stabilizing the rack Numbering the batteries Accessing your wiring diagramsAnchoring the rack optional Addressing the bottom shelf Positioning rails on shelvesWiring the batteries Rack Assembly Stud Terminal Addressing the second shelf Addressing the third shelfAddressing the top shelf Shelf-to-shelf wiring Assembling the second rack Employing sidecars to support separated racks Labelling the terminal blocksConnecting terminal blocks to battery breakers To Battery Breaker #1 BAT 1- terminal Connecting terminal blocks to batteries Rack #1, Top Shelf Terminal Block #1 Shelf-to-shelf From Battery #24 Rack #2, Top Shelf Terminal Block #2 Shelf-to-shelf From Battery #56 Grounding the racks Reattaching terminal block coversApplying warning labels APC GlossaryStyle E, rack #1, shelf #1 top Appendix a Battery Wiring Style EStyle E, rack #1, shelf #2 Style E, rack #1, shelf #3 Style E, rack #1, shelf #4 bottom Style E, rack #2, shelf #1 top Style E, rack #2, shelf #2 Style E, rack #2, shelf #3 Style E, rack #2, shelf #4 bottom References for Fiamm battery cables Appendix B Battery Cabling KitsReferences for Power battery cables Sidecar overview Appendix C Employing SidecarsPositioning and accessing the sidecar Connecting terminal blocks to sidecars To BAT To BAT 2+ Appendix C Employing Sidecars At the Sidecar Connecting sidecars to battery breakersBAT 2+ Top BAT BAT 1+ Top Battery Rack Assembly and Installation Manual Battery Rack Assembly and Installation Manual Battery Rack Assembly and Installation Manual APC Warranty on Batteries 03/2004 APC Worldwide Customer Support990-4194A