Parts List

This section provides a listing of parts needed to assemble each battery rack. Do not proceed with this installation until all parts are in your possession.

Description

APC P/N

Qty

 

 

 

Top Side Subassembly

870-1657A

2

 

 

 

Bottom Side Subassembly

870-1658A

2

 

 

 

Battery Rail

870-1696

16

 

 

 

Cross Bar (rack)

870-3698

8

 

 

 

Rear Cross Brace

870-3697

4

 

 

 

M12 x 35 Bolt

803-1235

14

 

 

 

M12 Nut

803-1200

14

 

 

 

12mm Lockwasher

812-0038

14

 

 

 

12mm Washer

812-0039

28

 

 

 

1/4-20 Spring Nut

812-0040

32

 

 

 

1/4-20 x 3/4” Socket Flathead Screw

812-0037

32

 

 

 

3/8-16 x 1” Bolt

812-0723

16

 

 

 

3/8 KEPS Nut

812-3101

16

 

 

 

3/8 Washer

812-2030

32

 

 

 

M6 Flange Nut

803-2406

1

 

 

 

M6 Serrated Washer

811-0604

1

 

 

 

Number Sheet Label

885-1617

1

 

 

 

Warning Label

 

4

 

 

 

CE Rating Label

885-1618

1

 

 

 

Battery Rack Assembly and Installation Manual

7

Image 13
Contents Assembly and Installation Manual Battery Racks for 400kW-1MW UPS SystemsBattery Rack Assembly and Installation Manual Contents Rack Assembly Appendix C Employing Sidecars Battery Rack Assembly and Installation Manual Safety warnings SafetySafety precautions Additional considerations Rack/battery options SpecificationsWeights and dimensions Shipping Shipping and ReceivingReceiving Positioning PlacementHandling Installation considerations Installation SiteInstallation equipment Torque specificationsAPC P/N Parts ListBattery Cabling Assembling the bottom section Rack AssemblyRefer to graphic in below Assembling the top section Top Side Subassembly #2 870-1657A Bottom Side Subassembly #2 Top Side Subassembly #1 Cross Bar #6 Top Side Subassembly #2 Connection Stabilizing the rack Anchoring the rack optional Accessing your wiring diagramsNumbering the batteries Addressing the bottom shelf Positioning rails on shelvesWiring the batteries Rack Assembly Stud Terminal Addressing the second shelf Addressing the third shelfAddressing the top shelf Shelf-to-shelf wiring Assembling the second rack Employing sidecars to support separated racks Labelling the terminal blocksConnecting terminal blocks to battery breakers To Battery Breaker #1 BAT 1- terminal Connecting terminal blocks to batteries Rack #1, Top Shelf Terminal Block #1 Shelf-to-shelf From Battery #24 Rack #2, Top Shelf Terminal Block #2 Shelf-to-shelf From Battery #56 Applying warning labels Reattaching terminal block coversGrounding the racks APC GlossaryStyle E, rack #1, shelf #1 top Appendix a Battery Wiring Style EStyle E, rack #1, shelf #2 Style E, rack #1, shelf #3 Style E, rack #1, shelf #4 bottom Style E, rack #2, shelf #1 top Style E, rack #2, shelf #2 Style E, rack #2, shelf #3 Style E, rack #2, shelf #4 bottom References for Power battery cables Appendix B Battery Cabling KitsReferences for Fiamm battery cables Sidecar overview Appendix C Employing SidecarsPositioning and accessing the sidecar Connecting terminal blocks to sidecars To BAT To BAT 2+ Appendix C Employing Sidecars At the Sidecar Connecting sidecars to battery breakersBAT 2+ Top BAT BAT 1+ Top Battery Rack Assembly and Installation Manual Battery Rack Assembly and Installation Manual Battery Rack Assembly and Installation Manual APC Warranty on Batteries 990-4194A APC Worldwide Customer Support03/2004