Installation Site
Installation considerations
The installation site should adhere to the following requirements:
•There should be ample room for performing rack assembly, battery installation, maintenance, and possible battery replacement.
•Aisle spacing should be in accordance with applicable code requirements.
•Racks should be set on a firm and reasonably level surface. Shimming up to a maximum of 6 mm [0.25 in.] may be used to level corner posts both
•Consider all requirements and restrictions with respect to floor loading.
•Batteries must remain in a
•Batteries should not be exposed to excessive moisture, construction dirt, corrosive elements, and other contaminants.
Installation equipment
Prior to assembling racks, ensure availability of the following tools and equipment:
• Open end/box wrenches (SAE dimensions) | • Battery lifting device (rated) | ||
• Ratchet set w/sockets (SAE | • Step ladder or stepping stool | ||
• Torque wrench | • Tape measure | ||
• | Standard, Phillips, and | • | Chalk line |
• | Concrete drill (for floor anchoring, if applicable) | • | |
• Voltmeter | • Level | ||
• Ohmmeter (for ground testing) | • Felt tip marker | ||
• | Floor shims (user supplied) | • | Protective boot (to cover cable lugs) |
Torque specifications
| STANDARD BOLT | BATTERY TERMINAL | ||||
|
|
|
|
|
| |
Bolt Diameter |
| Torque | Battery Type |
| Torque | |
|
| |||||
|
|
|
|
|
|
|
mm | inches | Nm | Brand | Nm | ||
|
|
|
|
|
|
|
6 | 1/4 | 7 | 60 | Power | 7.9 | 70 |
10 | 3/8 | 27 | 240 | Fiamm | 11.3 | 100 |
12 | 1/2 | 68 | 600 |
|
|
|
|
|
|
|
|
|
|
6 | Battery Rack Assembly and Installation Manual |