Operation

Series 4060

 

 

 

 

factory. If the ignition process fails, the instrument will attempt to ignite the flame 4 more times. If it continues to fail after the fifth attempt, a flame failure message will appear on the display. If this occurs refer to Section 5.

4.4.1 Verification of the Flame Guard Circuit

The operation of the flame guard circuit has been checked at the factory, but should be re-verified during start-up. Use the following procedure after ignition of the flame has been achieved:

1.Turn off the fuel at the supply cylinder.

2.Observe the fuel pressure gauge on the analyzer control panel. The gauge indication will decay as the fuel in the line is exhausted. When the gauge reading reaches near zero, the flame will extinguish as the fuel solenoid shuts off the fuel supply. The analyzer will automatically try to re-ignite. After 5 attempts, it will display: flame failure, check air, fuel and the flame failure LED will be on.

3.Open the cylinder supply valve and re-ignite the flame by pushing the up and down buttons simultaneously.

4.4.2Ignition and/or Flame Guard Circuit Failure

If the flame ignition or guard circuits do not operate as described in the above two sections, set the instrument fuel regulator to the recommended pressure. If still fails to ignite, proceed as directed in Chapter 5: Maintenance & Troubleshooting.

4.5 Sample Pump

A built-in sample pump is provided to draw sample gas from ambient air. The gas flow rate should be maintained at about 1000 to 1200 cc/minute using the Front Panel flow control valve (clockwise increases flow). See Figure 1-1.

4.6 Analyzer Operation

Although the Model 4060 has been programmed for your application at the factory, it can be further configured at the operator level. Depending on the specifics of the application, this might include all or a set of the following procedures:

44

Teledyne Analytical Instruments

Image 44
Contents Series Series Teledyne Analytical InstrumentsSafety Messages Teledyne Analytical Instruments IiiSeries Additional Safety Information Combustible GAS UsageSeries Procedure for Removal of Internal Inaccessible Shock Hazards Teledyne Analytical Instruments ViiViii Table of Contents Operation Maintenance & Troubleshooting Appendix Appendix BList of Figures Teledyne Analytical Instruments XiiiList of Tables Series Introduction Main Features of the AnalyzerIntroduction Introduction Series Principle of OperationAnalyzer Description Model 4060 Front Panel Interface Applications Operational Theory IntroductionModes of Operation Series Operational TheorySample System Analyzer SubsystemsOperational Theory Series Internal Temperature Controllers Gas Flow Control SystemFuel and Blanket Air Systems Flame Ionization Detection CellTypical Piping Diagram for the Model Detection Cell Electrometer-Amplifier Flame Ionization CellFlame Ignition Circuit Anode Power SupplyFlame Guard Circuit Installation Series InstallationUnpacking the Analyzer Mounting the AnalyzerInstallation Series Electrical Power ConnectionsUser Connections Electronic ConnectionsModel 4060 Rear Panel with Optional Gas Manifold Equipment Interface Connector Pin Arrangement Pin Function Threshold Alarm System Alarm Remote Calibration Connections Range ID Relay Connections Pin out of 50 pin D-Sub Connector 2.10 RS-232 PortCommands via RS-232 Input Gas ConnectionsGas Connections Less than 0.5 PPM Placing the System in Operation Series Operation OperationEquipment Operation Series Preliminary Power-Off Check ListActivating the Support Gases Flame Ignition 1 AirCarrier Gas Span GasSample Pump Analyzer OperationVerification of the Flame Guard Circuit Ignition and/or Flame Guard Circuit FailureSeries Operation Default Parameters Style ConventionsNavigation and Data Entry EnterEscape Menu StructureMain Menus Span Model Screen System Self-Diagnostic TestALT-SPAN Alarms Function AL-1 Defeated AL-1 High AL-1 NON-FAILSAFE AL-1 NON-LATCHING Operation Series Analog Output Adjustment Range FunctionChanging Stream Setting up an AUTO-CALLinearization Autocal Password Timing Group SetupPassword Protection Entering a Password Enter NEW Password Screen Repeat Password Entry Screen Logging OutStandby Series Operation Operation Series Teledyne Analytical Instruments Maintenance & Troubleshooting Series MaintenanceAnode Voltage Check Maintenance SeriesMeasuring Circuit Electrical Checks Printed Circuit Board Replacement Electronic StabilityTemperature Control Electronic Check Collector CableIgnition and/or Flame Guard Circuit Checks Sampling System Flame Guard and Anode Power Supply PCB Printed Circuit Board DescriptionsProportional Temperature Controller PCB Electrometer-Amplifier PCB Maintenance Series Series Appendix Specifications and Initial SettingsAppendix Analytical Instruments Recommended Spare Parts ListAppendix Series Drawing List PC Board AssembliesAppendix Series Teledyne Analytical Instruments B1 Addendum and Testing Results Appendix B