2.Touch System at the Station n Operator (or Pump n Setup) screen. The System Setup screen appears:

Note: Touching Help in the lower right of this screen gives you a menu of online help for the choices in this screen.

(7/50D Plus Screen shown)

Touching Return at the help menu brings you back to the System Setup screen.

3.Touch Stations Present in the upper left of the System Setup screen. A keypad pops up.

4.Enter the total number of stations (1–50) to be controlled by this controller. Use ← to erase any mistakes. Use ↵ to enter the value.

The keypad disappears and the new setting appears under Stations Present.

5.Touch Pumps Present in the upper part of the System Setup screen. A keypad pops up.

6.Enter the total number of pumps (1–7) to be controlled by this controller. Use ← to erase any mistakes. Use ↵ to enter the value.

7.The keypad disappears and the new setting appears under Pumps Present.

7/50D Plus or 7/50D Controller

Chapter 3: Installation

37

Image 38
Contents SCC 7-Pump 50D & D Plus-Station Controllers Parts and Service Department Shipping Information Table of Contents Maintenance Controller Safety Tags Safety Symbols Used in this Manual SafetyHow to Use This Manual Wear Safety Glasses and Work Gloves Responsibility General ResponsibilityOperator Responsibility Maintenance ResponsibilityReporting a Safety Defect General Description Functional DescriptionModels Covered in This Manual Electrical Features Standard FeaturesMechanical Features Controller FeaturesSafety Circuit Standards Optional FeaturesSafety Devices and Interlocks Fail Safe OperationSafety Device Lock-Outs Uncrating InstallationSystem Installation Overview Mounting the Control PanelRunning KwikLink Cables Making Control Panel Power Drop Wiring ConnectionsElectrical Connections About KwikLink Flat CablesInstalling KwikLink Cable Installing Assembled Mounting Plates Setting Up and Installing Mounting PlatesSetting Up Mounting Plates Terminating Cable Runs Discard the standard resistor cap to eliminate confusionInstalling Inside KwikLink Connectors with Blank Caps Proper Termination ConnectionsAddressing Armorblocks Addressing and Installing ArmorBlocksSetting Armorblock Addresses ArmorBlock Address RangesInstalling ArmorBlocks Using seal block to pierce cableSecuring the Seal Block to the Cable Base Installing KwikLink Connectors Connecting the Controller to the Network Connecting the Remote Interface to the Main ControllerProper Controller and Remote Interface Connections Connecting the Power Supply Enclosure to the Network Proper Power Supply Enclosure Connections Connecting Vacuum Receivers to the Network 50D 4-Connector ArmorBlock ConnectionsPlus Connections Connecting Vacuum Pumps and Filter Chambers to the Network Connecting Vacuum PumpsProper Vacuum Pump Connections Connecting Filter Chambers Proper Filter Chamber ConnectionsConnecting Central Alarms to the Network Proper Central Alarm ConnectionsAlarm Horn C-O1 Setup Basic Menu Flow for SetupSetting Up the System Setting the Number of Stations and the Number of Pumps50D Plus Screen shown Checking Addressing and Wiring for System Components Page Page Setting Up Alarm Silences Setting Up Pump Staging Setting Up Touch Switch DelaySetting Up Stations Setting Up a Single Station50D Plus shown Copying Settings from One Station to Others To copy the selected station’s settings to one other station Setting Up Pumps Setting Up a Single PumpPage Copying Settings from One Pump to Others To copy the selected pump’s settings to one other pumpTo copy the current pump’s settings to all other pumps Finishing Setup Setting Up Passwords Page Initial Startup Starting and Stopping the System OperationOverview Basic Tasks Reviewing Station StatusColor Label Description Reviewing Pump Status Color Label Description Logging On and Logging Off Enabling and Disabling Stations and Pumps Reviewing and Adjusting Basic Station Settings Reaching and Reading the Station Operator ScreensAdjusting Convey Time and Dump Delay Navigating among the Station Operator ScreensActivating and Stopping Priority Convey for a Station Changing the Mixture for a Remote Proportioning ValveAdvanced Tasks Changing the Line with Material ProofingReviewing and Resetting a Pump Hour Meter Transferring Stations to a Standby Pump Page Page Alarms Reviewing AlarmsClearing the Alarm Log Touch ContinueSilencing Alarms Corrective Maintenance MaintenancePreventative Maintenance Network Scanner Module ConsiderationsMemory Module Considerations Configurable SettingsOptions for Station Setup 50D Plus or 7/50D Controller Configurable Settings Blow Back Options Only available on 7/50D Plus systems Only available on 7/50D Plus systems 50D Plus or 7/50D Controller Configurable Settings Options for Pump Setup 50D Plus or 7/50D Controller Configurable Settings Troubleshooting General TroubleshootingStation Alarms Alarm message Possible causePump Alarms System Alarms Optional Components WarrantyAppendix Drawings and Diagrams Pump 50 station Controller with ??? DisplayTypical System Installation Layout 50D Plus or 7/50D Controller Appendix AC Voltage Spare Parts ListReturned Material Policy DC VoltageController Safety Tags Safety Tag InformationWarranty Returns Controller Identification Serial Number TagParts Department Service DepartmentTechnical Assistance Contact Information Sales Department