Navigating among the Station Operator Screens
The controls in the upper
1.To display the screen for the next
2.To display the screen for the next
3.To display the screen for a specific station, touch Goto. A keypad pops up. Enter the number for the desired station. Use ← to erase any mistakes. Use ↵ to enter the value.
4.To exit to the Station Summary (or Pump Summary) screen, touch Stations (or
Pumps).
Adjusting Convey Time and Dump Delay
Convey time is the length of time the station’s vacuum valve remains open to allow material to be drawn in. (For a
Dump delay is the length of time allowed for material to drain from the station into its receiver. During this time, the controller does not attempt to deliver any more material to the station.
The settings for convey time and dump delay should match the times actually required to fill and empty the station. The following problems may occur if these settings are incorrect:
1.Material is backing up and causing “high vacuum” alarms (for
2.System is not keeping up with the demand for material: Convey time is too short, or dump delay is too long.
For your reference, the Station n Operator screen shows the length of time the controller actually spent conveying material during the most recent delivery under Last Convey Time.
To adjust a station’s convey time (or the dump delay):
1.Go to the Station n Operator screen (as described on p. 61), or go to the Station n Setup screen.
2.Touch Convey Time (or Dump Delay). A keypad pops up.
3.Enter the number of seconds desired. Use ← to erase any mistakes. Use ↵ to enter the value.
The new setting appears under Convey Time (or Dump Delay).
Note: If you change convey time by more than a few seconds for a station with a remote proportioning valve (RPV), notify the setup personnel at your facility. The setting for the RPV’s cycle time should be adjusted to divide evenly into the new convey time (see pp. 43 and 77).
7/50D Plus or 7/50D Controller | Chapter 4: Operation | 62 |