1.Boiling Out of Boiler and System. Oil and grease which accumulate in a new hot water boiler can be washed out in the following manner.

a. Remove Safety Relief Valve using extreme care to avoid damaging it.

b. Partially fill boiler. Pour recommended compound into boiler through safety relief valve opening.

c. Replace Safety Relief Valve. d. Fill entire system with water. e. Start firing equipment.

f. Circulate the water through the entire system. g. Vent the system, including the radiation.

h. Allow boiler water to reach operating temperature, if possible.

i. Continue to Circulate the water for a few hours. j. Stop the firing equipment.

k. Drain the system in a manner and to a location that hot water can be discharged with safety.

l. Remove plugs from all available returns and wash the water side of the boiler as thoroughly as possible, using a high-pressure water stream.

m. Refill the system with fresh water.

n. Add recommended boiler water treatment.

2.Make pH or Alkalinity Test.

a. After boiler and system have been cleaned and refilled as previously described, test the pH of the water in the system. This can easily be done

by drawing a small sample of boiler water and testing with Hydrion paper which is used in the same manner as litmus paper, except it gives specific readings. A color chart on the side of the small Hydrion dispenser gives the reading in pH. Hydrion paper is inexpensive and obtainable from any chemical supply house or through your local druggist. The pH should be higher than 7 but lower than 11. Add recommended water treatment chemicals, if necessary, to bring the pH within the specified range. With this lower level of protection, care must be exercised to eliminate all of the free oxygen in the system.

b. Boiler is now ready to be put into service.

CONDENSATION — Following a cold start, condensation (sweating) may occur in a gas fired boiler to such an extent that it appears that the boiler is leaking. This condensation can be expected to stop after the boiler is hot.

O.Check Damper Operation - If boiler is equipped with vent damper, vent damper must be in open position when boiler main burners are operating. Start boiler, refer to instructions on damper to determine if damper is in full open position.

P.Review User's Information Manual and system operation with owner or operator.

Q.Post instructions near boiler for reference by owner and service personnel. Maintain instructions in legible condition.

61

Image 61
Contents 8141049R26-10/08 Price $5.00 IndependencePage Page Dimensional Drawing Table of Contents Probe L.W.C.O Float L.W.C.O Tankless Heater Pre-Installation Clearance to Combustible Materials Install Base-Burner-Manifold Assembly II. Knocked-Down Boiler AssemblyInstall assembled cast iron sections on base assembly Canopy Gasket Installation Install CanopyCombustion Chamber Intermittent Ignition EI Install Ignition Module Install Blocked Vent Switch with sheet metal screwsInstall Trim and Controls III. Semi-Pak Boiler AssemblyRemove Crate Steam Boiler with Probe Low Water CutoffWater Boiler Junction Box and Mounting Bracket AssemblyInstall Jacket Front Panel IV. Packaged Boiler AssemblyRemove Jacket Front Panel. See Figure Piping and Trim Page Recommended Water Piping for Circulator Zoned Heating System Recommended Water Piping for Zone Valve Zoned Heating System Recommended Piping for Indirect Water Heater Page Rated Input VI. Gas PipingConnect boiler gas valve to gas supply system Specific Gravity Correction Factors for Natural Gas Fitting Equivalent LengthsBoiler Equipped With Vent Damper VII. VentingIf an Existing Boiler is Removed Typical Vent InstallationVIII. Electrical Wire Vent Damper if usedAlliance Indirect Water Heater if used Thermostat Heat Anticipator SettingsVent Damper Harness to Limit This page Left Intentionally Blank Page Page Page Page Page Page Page Page Page Page Page Page Page Page Page Page Page Page Page Page Fill boiler with water IX. System Start-upPrepare to check operation Follow Lighting or Operating InstructionsPage Page Page Page Ignition Module Terminal Cross-Reference Ignition Module Wiring Ladder Diagram Terminal DesignationOFF Green LED Status CodesPilot Burner Flame, Honeywell Q350 Check low water cutoff steam only Adjust gas input rate to boiler. Natural GasDo not drain below gauge glass Check LimitInput Rate Adjust gas input rate to boiler. LP/PropanePage Page Maintenance of Low Water Cutoff Service InstructionsClean Boiler Flueways Boiler Flueway CleaningTankless Heater Pilot Burner LocationModel No Gallons Per Month Year Excessive Make-Up WaterHoneywell Electronic Ignition Trouble Shooting Guide Honeywell Hot Surface to Pilot Trouble Shooting Guide Avoid Breathing Fiber Particulates and Dust Service Record XI. Repair PartsSection Assembly Canopy and Draft Hood Canopy/Draft Hood Parts Base Tray Base AssemblyBurner Tray 1 Inch Main Burners Manifold and 1 Main Burners Manifold and Main Burners 1 Inch Main Burners Only Manifold and Main Burners 40MM Main Burners only Manifold and 40mm Main BurnersIntermittent Ignition Only Volt Continuous Ignition Standing Pilot Natural GasNatural Gas, High Altitude 5000-9000 Ft. USA Only LP Gas, High Altitude 2000-5000 Ft. USA OnlyLP Gas, High Altitude 5000-9000 Ft. USA Only Natural Gas, High Altitude 2000-4500 Ft. Canada OnlyPilot Burner, Honeywell Q350A1321 Pilot Burner, Honeywell Q348A1002 Page Jacket Assembly Front Top Panel Jacket Assembly Refer to Figure onSteam Trim Page Water Trim Quantity This page Left Blank Intentionally Page Blocked Vent Switch Flame Rollout SwitchTransformer Steam and Gravity Water Only Ignition Module Intermittent Ignition OnlyXII. Low Water Cut Off Lwco Wiring of Typical LwcoLwco Location Limited Warranty Limited Warranty