Hearth and Home Technologies PALOMA-GY, PALOMA-GR, PALOMA-BL, PALOMA-BZ Cathedral Ceiling

Page 19

H. Cathedral Ceiling

1.Follow installation Steps 1 and 2 under vertical instal- lation section, page 16.

2.Remove shingles or other roof covering as necessary to cut the rectangular hole for the support box. Cut the hole 1/8 in. (3 mm) larger than the support box outline.

3.Lower the support box through the hole in the roof until the bottom of the support box protrudes at least 2 in. (51 mm) below the ceiling (Figure 5.17). Align the support box both vertically and horizontally with a level. Temporarily tack the support box in place through the inside walls and into the roof sheathing.

LEVEL

CATHEDRAL CEILING

SUPPORT BOX

2 in. (51 mm) MIN. BELOW FINISHED CEILING

CUT HOLE 1/8 in. (3 mm)

GREATER IN SIZE THAN

PATTERN OF SUPPORT

BOX AS IT IS PROJECTED

ONTO ROOF LINE

Figure 5.17

4.Using tin snips, cut the support box from the top corners down to the roofline, and fold the resulting flaps over the roof sheathing (Figure 5.18). Before nailing it to the roof, run a bead of non-hardening mastic around the top edges of the support box to make a seal between it and the roof. Clean out any combustible material from inside the support box.

5.Assemble the desired lengths of pipe and elbows necessary to reach from the appliance up through the round support box. Ensure that all pipe and elbow connections are in their fully twist-locked position. Assemble as instructed.

Figure 5.18

6.Place the support clamp (provided with the support box) inside the support box (at the bottom), and secure to the pipe section. The clamp allows the support box to support the weight of the pipe sections. Continue to add pipe sections until you are above the roofline.

7.Complete the cathedral ceiling installation by following the same procedures outlined in steps 7 through 9 for vertical installations, pages 17-18.

8.Install the black trim collar around the outside of the cathedral ceiling support box (Figure 5.19). The two pieces of the trim collar slide over one another to allow for easy adjustment around the support box. Using the six screws provided, secure the four corners and the overlapping sections of the trim collar to the ceiling. You may want to predrill the holes for the overlapped sections for ease of installation.

TRIM COLLAR

CATHEDRAL CEILING

SUPPORT BOX

SCREWS

Figure 5.19

Heat & Glo • Paloma • 7031-220 Rev. P • 10/08

19

Image 19
Contents Hot glass will cause burns ModelsWhat to do if you smell gas Do DiscardnotHomeowner Reference Information CongratulationsTable of Contents Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGetting Started Installation to ensure maximum safety and benefitTools and Supplies Needed Model Framing and ClearancesSelecting Appliance Location Clearances to CombustiblesPaloma Surround Optional Stone Surround InstalledVent Termination Minimum Clearances Termination LocationsSee .4 for specific clearances Alcove Applications Measuring Standards Vent InformationVenting Components Use of ElbowsException for Rear Vent KIT Snorkel Kit SLK How to Use the Vent GraphSNKD, Horizontal Installation Venting GuidelinesFemale Locking Lugs Male Locking Horizontal Termination203 mm 178 mm 152 mm Vinyl Siding Vertical Termination Hole as shown in Figure Twist-lock the vent cap and seal Cathedral Ceiling Class a Metal Chimney Type a Existing Masonry ChimneyTo determine the length of flex needed, measure from Flex Liner Flex Coupler Sheet Metal Screws Slim Line Wall Thimble Installing Slim Line Trim Ring and Heat ShieldAssembling Slim Line Trim Ring and Heat Shield FIG. C Minimum Clearance Converting to LP Gas Procedure for ConversionGas Information Fuel ConversionsReattach Pilot Shield Verify the performance of the ignition system Gas PressuresPressure Natural Gas Propane Check for GAS Leaks Gas ConnectionWire Size Max. Length Recommendation for WireConnecting to the Appliance IntelliFire Ignition System WiringLoss of Power and Battery Backup Usage Junction Box Wired to Wall Switch Wall Switch Installation for Fan OptionalRemove Shipping Materials Appliance SetupUnbolting Appliance from the Pallet Leveling and Lagging Down the Appliance AccessoriesTop to Rear Vent Conversion Installing the Vent Restrictor Shutter AdjustmentPositioning the Logs Installing the BaffleMineral Wool Installation precautionsOptional Blower Black Wires Recommended operating procedures Variable Installing flame control solenoid Remote ControlsRemote receiver RED Orange Blue Wiring the flame control solenoidInner Glass Door Assembly Replacement Front Door Glass Assembly InstallationBefore Lighting Appliance Operating InstructionsControls Final inspection by Turn off all electric power to the applianceOn position. The ON/OFF switch may Lighting Appliance IPI IgnitionInitial Break-in Procedure Frequently Asked QuestionsAfter Appliance is Lit Symptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System flame has been lit, flame Maintaining and Servicing Appliance Inspect Maintenance Tasks Maintenance TasksLocation Inches Millimeter Appliance Dimension Diagram Without Stone SurroundReference Materials Hearth PadAppliance Dimensions with Stone Surround Appliance Dimension Diagram With Stone SurroundSLP Series Vent Components Vent Components DiagramMiscellaneous Vent Components ListService Parts Log Set AssemblyDescription Comments Part Number Service Parts ListStocked At DepotStocked Paloma Bottom Plate AssemblyCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Contact Information