Goodmans SSX, GSZ, ASZ, ASX, DSZ, DSX, GSX, SSZ manual Electric Heater Optional Item, Defrost Operation

Page 58

SERVICING

The outdoor fan will change to high speed operation. If the “Y2” demand is present and becomes satisfied, the thermostat will remove the “Y2” demand and the VSTB will remove the 24Vac from “Y/Y2” at the heat pump. The blower will drop to 60% of the programmed cfm and the outdoor fan will change to low speed. On most digital/ electronic thermostats, “Y2” will remain energized until the first stage heating demand “Y1” is satisfied and then the “G”, “Y1” and “Y2” demands will be removed.

4.3If the heat pump operation cannot satisfy the demand, the room thermostat energizes “W2/W3” and 24Vac is sup- plied to terminal “E/W1” of the VSTB inside the MBE/ AEPF unit. The VSTB will supply 24Vac to heat sequencer HR1 on the electric heater assembly.

4.4HR1 contacts M1 and M2 will close within 10 to 20 seconds and turn on heater element #1. At the same time, if the heater assembly contains a second heater element, HR1 will contain a second set of contacts, M3 and M4, which will close and turn on heater element #2.

Note: If more than two heater elements are on the heater assembly, it will contain a second heat sequencer, HR2, which will control the 3rd and 4th heater elements if available.

For the 3rd and 4th heater elements to operate on a second stage auxiliary heat demand, the PJ4 jumper on the VSTB inside the MBE/AEPF must be cut. If the “W2/ W3” demand cannot be satisfied by the heat pump, the temperature indoors will continue to drop. The room thermo- stat will then energize “W3/W4” and 24Vac will be supplied to “W/W2” of the MBE. The VSTB will supply 24Vac to HR2 on the electric heater assembly. When the “W3/W4” demand is satisfied, the room thermostat will remove the 24Vac from “W/W2” of the MBE/AEPF. The contacts on HR2 will open between 30 to 70 seconds and heater elements #3 and #4 will be turned off. On most digital/electronic thermostats, “W3/W4” will remain energized until the first stage demand “Y1” is satisfied and then the “G”, “Y1”, “Y2” “W2/W3” and “W3/W4” demands will be removed.

4.5As the temperature indoors increase, it will reach a point where the “W2/W3” demand is satisfied. When this happens, the room thermostat will remove the 24Vac from “E/W1” of the MBE/AEPF. The contacts on HR1 will open between 30 to 70 seconds and turn off the 1st and 2nd heater elements. If the “Y2” demand is present and becomes satisfied the room thermostat will remove the 24Vac from “Y/Y2” of the MBE and the blower motor will change to 60% of the programmed cfm. The VSTB will remove the 24Vac from “Y/Y2” at the heat pump and the outdoor fan will change to low speed operation. The heat pump remains on along with the blower motor because the “Y1” demand for first stage heat will still be present.

4.6When the first stage heat demand “Y1” is satisfied, the room thermostat will remove the 24Vac from “G” and “Ylo/ Y1” of the MBE/AEPF. The VSTB removes the 24Vac from “Ylo/Y1” at the heat pump and the compressor and outdoor fan are turned off. The blower motor will ramp down to a complete stop based on the time and rate programmed in the motor control.

5.0Defrost Operation

On heat pump units, when the room thermostat is set to the heating mode, the reversing valve is not energized. As long as the thermostat is set for heating, the reversing valve will be in the de-energized position for heating except during a defrost cycle.

5.1The heat pump will be on and operating in the heating mode as described the Heating Operation in section 4.

5.2The defrost control in the heat pump unit checks to see if a defrost is needed every 30, 60 or 90 minutes of heat pump operation depending on the selectable setting by monitoring the state of the defrost thermostat attached to the outdoor coil.

5.3If the temperature of the outdoor coil is low enough to cause the defrost thermostat to be closed when the defrost board checks it, the board will initiate a defrost cycle.

5.4When a defrost cycle is initiated, the contacts of the HVDR relay on the defrost board open and turns off the outdoor fan. The contacts of the LVDR relay on the defrost board closes and supplies 24Vac to “O” and “W2”. The reversing valve is energized and the contacts on HR1 close and turns on the electric heater(s). The unit will continue to run in this mode until the defrost cycle is completed.

5.5When the temperature of the outdoor coil rises high enough to causes the defrost thermostat to open, the defrost cycle will be terminated. If at the end of the programmed 10 minute override time the defrost thermo- stat is still closed, the defrost board will automatically terminate the defrost cycle.

5.6When the defrost cycle is terminated, the contacts of the HVDR relay on the defrost board will close to start the outdoor fan and the contacts of the LVDR relay will open and turn off the reversing valve and electric heater(s). The unit will now be back in a normal heating mode with a heat pump demand for heating as described in the Heating Operation in section 4.

S-60 ELECTRIC HEATER (OPTIONAL ITEM)

Optional electric heaters may be added, in the quantities shown in the specifications section, to provide electric resistance heating. Under no condition shall more heaters than the quantity shown be installed.

The low voltage circuit in the air handler is factory wired and terminates at the location provided for the electric heater(s). A minimum of field wiring is required to complete the instal- lation.

Other components such as a Heating/Cooling Thermostat and Outdoor Thermostats are available to complete the installation.

The system CFM can be determined by measuring the static pressure external to the unit. The installation manual supplied with the blower coil, or the blower performance table in the service manual, shows the CFM for the static mea- sured.

58

Image 58
Contents Service Instructions Important Information Recognize Safety SYMBOLS, Words and LabelsEmail us at customerservice@goodmanmfg.com Fax us at 713 Fax us at 931 438Safe Refrigerant Handling Product Identification Split System Heat Pumps R410AModel # Description Split System Air Conditioners R410A ASX130**1AA Single Piece Air Handlers AWUF****1AA MBR/MBE Air Handlers Product Identification 1824 3642 Accessories ASX13DSX/SSX16 ASX18 ASZ13 DSZ/SSZ16 ASZ18 Expansion Valve Kits FSK01A Coil Accessories Electric Heat Kitapplications Aruf Electric Heat Kitapplications Aepf Product Design Condensing UnitFigure a Capacity Control Cooling System OperationHeating Cooling CycleDefrost Cycle Heating CycleCooling Cycle System Operation AFE18-60A Control Board DescriptionTroubleshooting Chart COOLING/HP Analysis ChartServicing 61B3A Thermostat and Wiring Checking WiringChecking THERMOSTAT, WIRING, and Anticipator Checking Voltage3B Cooling Anticipator 3C Heating AnticipatorChecking Transformer Control Circuit Checking Time Delay RelayTesting Coil Circuit Checking Cycle ProtectorChecking Contactor AND/OR Relays Testing Compressor ContactorSingle Phase Checking Contactor ContactsCopeland Comfort Alert Diagnostics Testing FAN RelayDiagnostics Table Checking LOW Pressure Control Checking Loss of Charge ProtectorChecking High Pressure Control Checking Capacitor15B Capacitance Check 15A Resistance CheckRELAY, Start 16A Checking FAN and Blower Motor Windings PSC Motors 16B Checking FAN and Blower Motor ECM MotorsChart on Next Chart from Previous 16D ECM CFM Adjustments MBE / Aepf 16C Checking ECM Motor WindingsCFM 16F Checking GE X13TM Motors 16E Blower Performance DataGE X13TM Motor Connections 17A Resistance Test Testing Compressor WindingsChecking Compressor 17B Ground Test17D Operation Test 17C Unloader Test ProcedureUnloader Test Procedure Compressor Ground TestTesting Defrost Thermostat Testing Crankcase Heater Optional ItemTesting Defrost Control Checking Reversing Valve and SolenoidChecking Heater Elements 40 MBR/AR*F Electronic Blower Time Delay RelayChecking Heater Limit Controls Sequence of OperationMBR/AR*F with Single Stage Heat Pumps Heating OperationDefrost Operation 41 MBE/AEPF with GSX, SSX, ASX, DSXMBE/AEPF with Single Stage GSX, ASX and SSX Condensers 41A MBE/AEPF with Single Stage GSZ, SSZ, & ASZ Heat Pumps Sequence of Operation MBE/AEPF with TWO Stage ASX & DSX CondensersMBE/AEPF with TWO Stage ASZ & DSZ Heat Pump Units Electric Heater Optional Item 61B Checking Heater Fuse Link Optional Electric Heaters 61A Checking Heater Limit ControlsFormulas Evacuation Leak Testing Nitrogen or NITROGEN-TRACEDRefrigeration Repair Practice Brazing MaterialsCharging EvacuationFinal Charge Adjustment Checking Compressor Efficiency105B Thermostatic Expansion Valve TXV ValvesPressure vs. Temperature Chart 410A Required Liquid Line Temperature Superheat OverfeedingUnderfeeding Checking SubcoolingFixed Orifice Restrictor Devices 109A TWO Speed ApplicationChecking Expansion Valve Operation Subcooling Formula = Sat. Liquid Temp. Liquid LineNON-CONDENSABLES Checking Restricted Liquid LineOvercharge of Refrigerant Compressor BurnoutLong Line SET Application R-410A Accessories for lines greater than 80 feetRefrigerant Piping Tube SizingInstallation Requirements AIR Handler External Static Initial System ChargingTotal External Static Coil Static Pressure DropStatic Pressure Drop Accessories Wiring Diagrams ALL Fuel System AFE18-60A Control Board10kw and Below, One Stage Electric Heat OT/EHR18-60 #2 GRD PLM PLF XFMR-R XFMR-C After Installing Optional Heat KIT, Mark AN X Provided Above HKR Heat Kit GRD PLM PLF