American Power Conversion SYMSTRF Remove Packing Materials, Remove the Frame from the Pallet

Models: SYMSTRF SYMINIF SYMSTRF-PD SYMINIF-PD

1 75
Download 75 pages 19.36 Kb
Page 25
Image 25

Chapter 3 - Unpacking and Installing Frame

Remove Packing Materials

Note: It is recommended that all packaging materials be re- moved, and temporarily stored, in case any of the system com- ponents must be returned to the factory.

1.Remove the Shipping Bands - Using appropriate precau- tions, carefully cut the plastic shipping bands.

2.Removing the Plastic Wrap - Using care to not damage the surface of the Power Array, cut off the plastic wrap by running the tip of a sharp utility knife along the surface of one of the cardboard corner supports. Remove the plastic wrap from the frame.

3.The Pallet Ramp - The pallet ramp is shipped under the cardboard cap, on top of the frame. It will sometimes become wedged inside the cardboard cap. Use caution removing this cap from the frame. Remove the ramp from the top of the frame.

4.Corner Supports - When the cardboard cap is removed, the four corner supports will fall away. Remove them, and place to one side.

5.Remove the Cover Grills - Remove the grill covers from the frame. Grasp each grill cover by the side finger hold that is molded into them. Pull straight forward. Set the covers to one side. Be careful not to scratch them.

6.Leveling Feet - Fully retract each of the four leveling feet located near the casters on the bottom of the frame.

Fig 3-2Frame Restraint and Ramp Holes

Remove the Frame from the Pallet

1.Loosen Rear Bracket Screws - Loosen the two phillips- head screws securing the brackets at the rear of the frame.

2.Remove Two Pallet Restraint Screws - See Figure 3-2. Re- move the two phillips-head, pallet restraint screws. Use the cloth handle to remove the frame restraint from the pallet. Place the frame restraint and two screws to one side.

3.Install the Ramp - Position the ramp so that the installation bolts line up with the ramp bolt holes on the pallet. Install the ramp onto the pallet as shown in Figure 3-3.

Fig 3-3Frame Pallet Ramp

4.Roll the Frame from the Pallet - The following operation requires two people. Holding the frame near the center, care- fully roll it down the ramp, and onto the floor. (The frame is equipped with casters.)

5.Roll the Frame to the Installation Site - Carefully roll the frame from the staging area to the final installation site.

6.Shipping Material Storage - Gather all shipping materials together, and store it temporarily, in case any system compo- nent must be returned to the factory.

Moving Battery & Power Modules

1.Moving All Modules On Pallet - Using the pallet jack, move the modules pallet(s) to the installation site. If necessary, the modules can be moved one at a time. Remove all outer pack- aging materials from pallet, and carry each boxed module to the final installation site.

3.Stack Modules - Carefully stack the battery and power modules near the installation site. Leave enough room for the electrican to install the wiring to the frame.

Clean-UP

1.Packaging Materials - Remove all packaging materials from the installation site. Store it temporarily, so that it will be available if any components must be returned to the factory.

2.Final Inspection - Check the module bays of the frame to make sure they are clear of debris.

3-2

Page 25
Image 25
American Power Conversion SYMSTRF-PD, SYMINIF-PD Remove Packing Materials, Remove the Frame from the Pallet, Clean-UP