Chapter 5 - System Setup
Installing the Battery Modules
νEach battery module weighs 60 lb. Battery module installation and handling requires two people to lift the module.
Procedure for Battery Module Installation
1.Clear all battery module bays of any debris. Make sure the alignment tracks are clear, and free of obstruction.
Battery |
Module |
Bays |
Battery
Module
Fig 5-2 Location of Battery Module Bays
2.There are two alignment grooves molded into the bottom of the battery module bay. These correspond with runners that are molded into the bottom of the battery module.
See figure
Alignment Grooves
Retaining Notch |
Battery Module |
Retaining Flange |
Runners |
Fig 5-3 Battery Alignment Grooves and Runners
3.With one person on either side of the battery module, lift the module, align the runners with the alignment grooves, and slide module into the bay.
Note: When installing power or battery modules, always install them in the lowest available bays. Installing modules in this manner minimizes lifting, and lowers the center of gravity of the Power Array system.
4.As the battery module slides into the bay, the retaining flange will fall behind the notch in the frame. See figure
Fig 5-4 Battery Module Retaining Flange
5.To engage the internal electrical connector, the battery mod- ule must be swiftly and firmly pushed into place. The design of the battery module incorporates a “drop lock” that will engage when the battery module is properly seated in the bay. If the internal connector does not engage, a slight tug will move the module. If it is locked, the battery module will not move, and must be slightly lifted before it can be pulled from the bay.