Power-Up Procedure

Installing the ET10000A

Power-Up Procedure

Follow the instructions in this section to safely apply power to the ET10000A.

Figure 40 Dual power supplies on the ET10000A rear panel

Elements of Figure 40:

1)Status LED for power supply 2

2)Status LED for power supply 1

3)Power receptacle for power supply 2

4)Power receptacle for power supply 1

To power on the ET10000A:

1On the appliance’s rear panel, plug the power cords into the power receptacles for each power supply.

2Attach the opposite end of the first power cord to a power source. Attach the second power cord to a a power source on a different circuit. The power supply status LED illuminates when power is applied.

When the appliance powers up, all of the front panel LEDs illuminate (see Figure 41). The Alarm LED illuminates briefly and the diagnostic code LED displays 88 to verify that the diagnostic display segments are functioning. The power LED remains lit until the unit is powered off. The Power Supply LEDs illuminate for each operational power supply.

During the boot process the ET10000A cycles through its startup tests, and the corresponding diagnostic codes are displayed. After the tests execute successfully, the diagnostic code display is solidly illuminated with code 00.

Figure 40 Dual power supplies on the ET10000A rear panelTo power on the ET10000A:Manual background NOTE

During the boot process the ET10000A discards all traffic on its data ports. Once the appliance is operational, the default mode of operation passes all packets in the clear until you deploy security policies.