22.Installation of Top Front Jacket Panel
a.Remove knockout for supply piping (right or left for water boilers – both knockouts for steam boilers) refer to recommended boiler piping diagrams in this manual.
b.Attach Top Front Jacket Panel to left and right end Jacket Panel and to Top Flange on the Vestibule Panel using #8 SMS. See Fig. 22.
23.Installation of left and right top side Jacket Panel
a.Remove knockout, right or left, only if needed. (See Fig. 7 for purpose of tappings), secure top side panels to upper end panels with #8 SMS.
24.Install Knobs on the four remaining panels using
25.Install Upper Front, Lower Front, Upper Rear and Lower Rear Panels using procedure described in detail “A” of Fig. 23.
CAUTION
Panel with louvers must be at front of boiler for ventilation of vestibule. Panel with perforations must be at front of boiler for ventilation and combustion air.
26.Tighten all sheet metal screws.
27.Install the following plates or labels which are found in the Instruction Envelope. See Fig. 19 or 22 for location.
(1)Rating Label
(2)Operating Instruction Plate (#8 SMS required to fasten)
(3)Combustible Clearance Flooring & Adequate Combustion Plate
(4)Minimum Service Clearance Label
(5)Burnham Logo
(6)Boiler Ventilation For Your Safety Label – Apply to Top Panel
(7)Proceed to Paragraph 33 (Steam Boilers) or Paragraph 34 (Water Boilers).
COMPLETION OF JACKET INSTALLATION 11 THRU 26 SECTION BOILERS.
28.Paragraphs 1 thru 4 have already been completed. Refer to Paragraph 16 for installation of lower framework.
a.Install Vestibule Panel(s) – refer to Fig. 19 and 22.
Attach Hex Couplings to end of Carriage Bolts which secure Flue Cover Plates.
NOTE: Select Carriage Bolts which line up with holes in the Vestibule Panel(s).
b.Attach Intermediate Vestibule Panel(s) to one of the Vestibule Panel(s) using #8 SMS.
c.Secure Left and Right Vestibule Panels to Hex Couplings using
d.Attach the Lower Rear Intermediate Panels to the Lower Rear Intermediate Panel Support Bracket(s) using
e.Attach the Upper Rear Intermediate Panel(s) to the Lower Rear Intermediate Panel(s) using #8 SMS.
f.Attach Rear Top Intermediate Jacket Panel(s) to Rear Top Left and Right Jacket Panels using #8 SMS.
g.Place Assembled Rear Top Jacket Panel in position and attach to Upper End Panels and Upper Rear Intermediate Panel using #8 SMS.
a.INSTALLATION OF
11 THRU 26 SECTION BOILERS – these boilers require two or more
– refer to Fig. 6 for proper arrangement.
Determine where ends of
Cerafelt strips on top of intermediate section at these locations. Place Cerafelt strips on top of section assembly next to ledges formed by center sections and next to ledges on end sections.
Overlap at corner.
b.SECURE
21. Select the type of fastener indicated and drive them into the Tapped Lugs provided for this purpose on top of the sections. Where two
c.Attach the Front Intermediate Panel to the Front Intermediate Panel Support Bracket(s), using
29.Installation of Top Front Jacket Panels
a.Remove knockout for supply piping. Refer to recommended boiler piping diagrams in this manual.
b.Attach Top Front Jacket Panels to left and right end
Jacket Panels and also to top flange on the Vestibule
Panel using #8 SMS. Refer to Fig. 23 or 24.
30.Place Top Intermediate Panel(s) on top of left and right Panels, making sure that Front Intermediate Panel(s) is under Top Intermediate Panel(s). Secure Top Intermediate Panel using #8 SMS.
31.Install Knobs on the Upper Front and Upper Rear Panels using
Install Upper Front, Lower Front, Upper Rear and Lower Rear Panels using procedure we described in detail “A” of Fig. 23 or 24.
CAUTION
Panel with louvers must be at front of boiler for ventilation of vestibule. Panel with perforations must be at front of boiler for ventilation and combustion air.
25