DUAL MANIFOLD BASES - 5015B THRU 5026B SECTION BOILERS

a. Carefully join a Center Section with nipples in adjoining section and bump lightly to secure.

b. Run nut approximately 8” on two (2) ¾” draw-up rods of equal length. (Note – more than one set of draw-up rods are furnished on 8 section and larger boilers). Place draw-up channel and one flat washer against nut.

c. Insert short end of draw-up rod through front & rear nipple ports on both sections, see Fig. 5.

d. Place two (2) flat washers, draw-up channel and a nut on each end of draw-up rods and finger tighten.

Fig. 4

LEH SECTION ON BASE

Fig. 5

ASSEMBLY OF CENTER SECTIONS