UNIT START-UP CHECKLIST

UNIT START-UP CHECKLIST

MODEL NO.:

 

SERIAL NO: _____________________________________

DATE:

______________

TECHNICIAN: ___________________________________

I. PRE-START-UP:

jVERIFY THAT ALL PACKAGING MATERIALS HAVE BEEN REMOVED FROM UNIT j VERIFY INSTALLATION OF OUTDOOR AIR HOOD

j VERIFY INSTALLATION OF FLUE EXHAUST AND INLET HOOD (48PD ONLY)

j VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS j VERIFY THAT ALL ELECTRICAL CONNECTIONS AND TERMINALS ARE TIGHT

j VERIFY GAS PRESSURE TO UNIT GAS VALVE IS WITHIN SPECIFIED RANGE (48PD ONLY) j CHECK GAS PIPING FOR LEAKS (48PD ONLY)

j CHECK THAT INDOOR-AIR FILTERS ARE CLEAN AND IN PLACE j CHECK THAT OUTDOOR AIR INLET SCREENS ARE IN PLACE j VERIFY THAT UNIT IS LEVEL

j CHECK FAN WHEELS AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND VERIFY SETSCREW IS TIGHT j VERIFY THAT FAN SHEAVES ARE ALIGNED AND BELTS ARE PROPERLY TENSIONED

j VERIFY THAT SCROLL COMPRESSORS ARE ROTATING IN THE CORRECT DIRECTION j VERIFY INSTALLATION OF SPACE SENSOR

j VERIFY CONFIGURATION VALUES FOR ELECTRONIC CONTROLS (REFER TO CONTROL SET UP CHECKLIST) j VERIFY THAT CRANKCASE HEATERS HAVE BEEN ENERGIZED FOR AT LEAST 24 HOURS

j VERIFY THAT THE VFD IS IN AUTO MODE

II.START-UP

ELECTRICAL

SUPPLY VOLTAGE

L1-L2

L2-L3

 

L3-L1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

COMPRESSOR AMPS—COMPRESSOR A1

L1

 

L2

 

 

L3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

—COMPRESSOR B1

L1

 

L2

 

 

L3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

—COMPRESSOR C1

L1

 

L2

 

 

L3

 

 

 

 

 

 

 

 

 

 

 

 

 

ELECTRIC HEAT AMPS (IF EQUIPPED)

L1

 

L2

 

 

L3

 

 

 

 

_______

 

 

 

 

 

 

 

 

 

 

SUPPLY FAN AMPS

 

L1

 

L2

 

 

L3

 

 

 

 

 

 

 

 

 

 

TEMPERATURES

OUTDOOR-AIR TEMPERATURE

 

 

F DB (Dry Bulb)

 

RETURN-AIR TEMPERATURE

 

 

F DB

F WB (Wet Bulb)

 

 

COOLING SUPPLY AIR

 

 

F

 

 

 

 

GAS HEAT SUPPLY AIR (48PG)

 

 

F

 

 

 

 

ELECTRIC HEAT SUPPLY AIR (50PG)

 

 

F

 

 

 

 

 

 

 

PRESSURES

GAS INLET PRESSURE

 

 

IN. WG

 

 

 

GAS MANIFOLD PRESSURE

STAGE NO. 1

 

IN. WG

STAGE NO. 2

 

IN. WG

 

 

REFRIGERANT SUCTION

CIRCUIT A

 

PSIG

 

 

 

 

 

 

 

 

CIRCUIT B

 

PSIG

 

 

 

 

 

 

 

 

 

CIRCUIT C

 

PSIG

 

 

 

 

 

 

 

 

REFRIGERANT DISCHARGE

CIRCUIT A

 

PSIG

 

 

 

 

 

 

 

 

CIRCUIT B

 

PSIG

 

 

 

 

 

 

 

 

 

CIRCUIT C

 

PSIG

 

 

 

 

 

 

 

 

 

 

 

 

 

jVERIFY REFRIGERANT CHARGE USING CHARGING CHARTS

GENERAL

jECONOMIZER MINIMUM VENT AND CHANGEOVER SETTINGS TO JOB REQUIREMENTS

48/50PD