12. PROCESSING OF HEATING PIPE ENDS

12.1 Outline

(1) Configuration

Power supply 100VAC, 50/60Hz

Power connection kit

About 2000

Heating pipe

Termination kit

About 500

Fig. 12-1

(2)Caution on connection of heating pipe

q The clearance between clamp supports must be about 1.2 m in the horizontal direction and about 3 m in the vertical direction.

w For a bent piping, bending should be moderate enough to ensure a minimum bending radius of 300 mm or more.

Clamp support

No good

Good

Fig. 12-2

(3)Connection diagram

A heater wire is wound around 2 isolated buses and it is brought into contact with the buses alternately at intervals of 300 mm (heating unit).

Power supply

Heating wire

300mm

300mm

300mm

300mm

300mm

300mm

 

 

Fig. 12-3

 

 

 