g
GE
7.1.3 From Manual Bypass (Q2) to normal function
Initial status:
Load supplied from Manual Bypass.
1.Close Q1 (Pos. I).
•Bypass connects to Load. LED Load on Bypass lights up.
•Rectifier starts automatically and LED in Rectifier symbol and LED Battery charge light up.
2.Open Q2 (Pos. O).
•LED Manual Bypass turns OFF.
3.Connect the Battery to the UPS by closing the Battery Switch or Fuses, in case of External Battery .
4.Press “inverter on” ( I ) key.
•
•At the end of
•Automatic transfer from Bypass to Inverter.
•UPS output LED indicates Load on Inverter.
The LCD must display on the main screen the status “LOAD ON INVERTER”.
End of procedure
OPM_SGS_USM_10K_40K_0US_V010.doc | 45/88 | Operating Manual SG Series 10, 20, 30 & 40 kVA |